Architecture Overview

This page describes the architecture of TruePPM as it exists today. The scheduling engine, API, real-time layer, web frontend, and the 0.2 settings/administration and program platform are all functional as of 0.4 — 0.4 is TruePPM’s first beta (v0.4.0-beta.1, September 15, 2026), and the newest pre-release is on the Releases page. The first beta layered the read-only MCP server, basic single sign-on, and in-app time capture and baselines on top of the 0.3 agile-team feature set and the v2 interface refresh.

task

publish

REST

WebSocket

enqueue

broadcast

Django ASGI process (uvicorn)

DRF ViewSetsREST API

Django ChannelsWebSocket consumers

React web + mobile(API clients)

Valkey

Celery workerCPM auto-scheduler

PostgreSQL 16

How to read it. Solid arrows are direct PostgreSQL reads and writes; dotted arrows are asynchronous messages passed through Valkey, which is both the Celery broker and the Django Channels layer. PostgreSQL stores every project, task, and the WBS hierarchy as an ltree column with a GiST index for subtree and ancestor queries.

Follow a schedule change end to end: a write through a DRF ViewSet enqueues a reschedule on the Valkey broker; the Celery worker runs the CPM engine, writes the new dates to PostgreSQL, and publishes the result back through Valkey; Django Channels picks that up off the channel layer and fans it out to every connected client over its WebSocket.

Every feature is a REST or WebSocket endpoint before it is a UI element. Web and mobile clients have no privileged access — they are API consumers identical to any third-party integration. The OpenAPI schema at /api/schema/ is the authoritative contract.

The authoritative value of any persisted fact — including every scheduled date, float, and Monte Carlo forecast — is always computed server-side and reached over the API. Three narrow compute paths deliberately run outside the API, each bounded by one invariant: the server always has the last word.

  1. The interactive schedule preview. Dragging a Gantt bar (or rescheduling with the keyboard) recomputes the affected downstream dates in the browser with no API round-trip, because a request per pointer-move could never stay interactive. That preview is a best-effort, lower-fidelity estimate — it is never persisted, and the authoritative server CPM reconciles the real dates on commit.
  2. On-device / offline recompute. When there is no network, the API cannot be first, so the client will recompute locally. This is what the Rust/WASM CPM engine is for: it is held in conformance with the Python engine in CI so an offline result will match what the server would compute, and the server still reconciles on reconnect. Wiring that engine into the browser and mobile app is future work (#1777) — the shipped preview above runs a TypeScript CPM port until then.
  3. The engine as a library. trueppm-scheduler and its Rust sibling are usable with no API at all (see Scheduling as a separate package).

The rule of thumb: if a value is authoritative — if a persisted fact depends on it — it lives server-side behind the API. If it is a discardable preview or an offline stand-in the server will reconcile, it may run at the edge. See ADR-0599 for the full boundary.

The AI-native foundation — see AI-native by design for the consolidated view aimed at agent builders. Every incumbent is bolting an LLM onto a project database and letting the model guess dates. TruePPM takes the opposite stance, and it has a name: computed, not guessed. An AI-surfaced answer is never the language model’s opinion — it is a CPM or Monte Carlo computation the engine performed, carrying a server-side derivation you can cite. The model’s only job is to translate a question into an engine call and to phrase the engine’s answer back in natural language. It never supplies the number.

This is an architectural commitment, not a feature toggle. It is why the scheduling engine is a separate, deterministic package and why every feature is an API fact first: if a value is computed server-side and reachable over the API, an agent can retrieve it and cite it; if it lived only in a chat prompt, the agent could only guess at it.

TruePPM — computed, not guessed

Question

NL layer(translates to a call)

Engine call(CPM / Monte Carlocomputes)

Provenance-carrying answer(e.g. P80 is Oct 22, derivedfrom this critical chain —citable)

Incumbent — the LLM is the answer

Question

LLM

Asserted answer(a plausible guess;no derivation to check)

The principle is sequenced across the roadmap as one capability with four parts — compute, cite, refuse, reproduce — not four scattered AI bullets (see the roadmap):

  • Compute / cite — provenance graph (#1058) — every computed date, float, and P80 carries the derivation an agent can cite, so an answer is explainable, not asserted. It shipped with the 0.4 read-only MCP server.
  • Reproduce — agent-action audit foundation (#1805, ADR-0112 Accepted) — every agent read and every verdict is recorded in a hash-chained, audit_verify-checkable log; it also shipped with the 0.4 beta. A signed engine-version + input-hash answer stamp (#1065) follows at 0.9.
  • Natural-language query layer (#1060 #1061, planned for 0.5) — compiles a question into engine calls, never into an answer; the model translates, the engine answers.
  • Refuse — safe agent writes (#1062–#1064, planned for 0.6) — an engine-as-referee refuses any agent write that would create an impossible schedule, identically to a human write; this is the refuse verb reaching the write side.

The deterministic engine behind all four verbs is shipped today; the compute, cite, and reproduce foundations shipped with the 0.4 beta. The dates above are targets, not commitments — the roadmap is the source of record for what has shipped versus what is planned.

The API exposes a WatermelonDB-compatible sync endpoint (GET /api/v1/projects/{pk}/sync/) returning changes and deleted arrays keyed by server_version. This is designed for future mobile and PWA clients — see Offline Sync for details.

The CPM and Monte Carlo engine lives in packages/scheduler (trueppm-scheduler on PyPI), completely independent of Django. This means:

  • The engine can be used without the API (embedded in other tools and scripts); a Rust sibling (packages/wasm-scheduler) compiles to WASM and is held in conformance with it in CI, for future on-device scheduling (#1777)
  • The engine has its own test suite and release cycle
  • Algorithmic correctness can be validated without a running database

The Celery worker imports trueppm-scheduler as a library, fetches project data from PostgreSQL, calls schedule(), and writes CPM output fields back.

Every synced model extends VersionedModel:

class VersionedModel(models.Model):
id = models.UUIDField(primary_key=True, default=uuid.uuid4)
server_version = models.BigIntegerField(default=0)
is_deleted = models.BooleanField(default=False, db_index=True)
deleted_version= models.BigIntegerField(null=True, blank=True)

server_version starts at 1 on INSERT and increments atomically on every UPDATE via an F() expression to avoid lost-update races. Deletes are soft: the row is retained with is_deleted=True so mobile clients receive a tombstone on the next sync pull.

Every mutation is followed by a broadcast_board_event() call deferred inside transaction.on_commit(). This ensures:

  1. The broadcast only fires if the database transaction committed successfully
  2. WebSocket clients receive the event as a push, not a poll

REST + WebSocket

REST + WebSocket

REST, read-only

pip, >=0.4,<0.5

CI conformance

planned, not wired (#1777)

packages/webReact 19 client

packages/mobilescaffold, not built

packages/mcpread-only MCP server

packages/apiDjango + DRF + Channels

packages/schedulertrueppm-scheduler

packages/wasm-schedulerRust + WASM

Solid arrows are dependencies that exist today (the arrow points at what is depended on); dashed lines are a scaffold, a CI-only check, or planned work, and packages/wasm-scheduler is not yet used by any client.

Pure-Python. Dependencies: networkx (graph), numpy (Monte Carlo). Ships on PyPI as trueppm-scheduler. See Scheduling as a separate package above — this page does not document the engine’s internals.

The CPM engine’s Rust sibling: a petgraph-based implementation compiled to WebAssembly with wasm-pack (crate trueppm-wasm-scheduler). It exists for future on-device / offline scheduling (#1777) — a browser or mobile client with no network still needs to recompute dates locally. CI holds it in behavioral conformance with packages/scheduler (scheduler:snapshot-regression), and gates it with wasm:lint (clippy -D warnings), wasm:test, and wasm:license-check (deny.toml). It is not wired into the web or mobile client and is frozen: no new feature work lands in it until the decision on its fate (#4743), due no later than 0.6 planning. Its output is advisory and never produces a refusal; it cannot see summary-task structure (see ADR-0599). See API-first for why an unwired offline engine doesn’t compromise the “server always has the last word” invariant.

A scaffold, not a working client — this section describes the package as it exists today, and today it is a shell. React Native (0.81) bare workflow (not Expo managed — native modules and app-store-only enterprise releases rule it out), TypeScript, NativeWind (Tailwind for React Native). src/navigation/ and src/features/ are implemented: a five-tab bottom-tab shell over placeholder screens. src/db/, src/sync/, src/auth/, and src/api/ are typed boundaries only — they declare the contracts the offline store, delta-sync client, token storage, and HTTP client will satisfy, and nothing implements them yet (#41). There are no native android/ or ios/ projects, so the package cannot be built or installed, and there is no test suite; CI gates it with lint and type-check alone. No native app is scheduled: the installable PWA is the mobile story through 1.0, and a native app returns to a numbered release only when people running TruePPM report a mobile workflow the PWA cannot serve (see the roadmap).

A read-only Model Context Protocol server (trueppm-mcp), Apache 2.0, with its own pyproject.toml and Dockerfile — a pure HTTP client of the TruePPM REST API with no Django dependency and no direct database access. It ships the read-tool surface designed in ADR-0186 (stdio transport by default; --transport http for network use). See Computed, not guessed above for how it fits the AI-native foundation, and MCP server for the feature-level documentation.

React 19 + TypeScript + Vite 8. Tailwind CSS with Design System v2.0 (navy/sage) tokens (WCAG 2.1 AA). TanStack Query for server state, Zustand for client state, React Router v8. The Schedule view (Gantt-style) uses a purpose-built canvas renderer in src/features/schedule/engine/ (no third-party Gantt library). The application shell, Schedule, Board, Sprints, and supporting views are wired against the live API.

Django 5.2 + DRF 3.15. Django Channels 4 (ASGI). Celery 5.4 + Valkey (BSD-licensed Redis fork; wire-compatible). django-allauth + simplejwt. drf-spectacular (OpenAPI 3.0.3). PostgreSQL 16 with ltree for WBS hierarchy.

Valkey serves three distinct roles, each on its own logical database index off the same REDIS_URL (settings/base.py): the Celery broker/result backend (/0), the Django Channels layer backing WebSocket fan-out (/1), and — the role most easily missed — the Django CACHES["default"] backend (/2), which holds short-lived OIDC/OAuth2 state (the PKCE verifier, nonce, and exact redirect_uri for an in-flight SSO login — see apps/sso/services.py) and backs every DRF scoped throttle counter (login, refresh, Monte Carlo, and the general anon/user rate limits).

This Astro Starlight site. Built with npx astro build; deploys to GitLab Pages.

Helm 3 chart with vendored first-party sub-charts for PostgreSQL and Valkey (under packages/helm/charts/, using the official postgres and valkey/valkey images). Separate values-dev.yaml and values-prod.yaml overlays.

register against

trueppm-suite · Apache 2.0

Community coreAPI, scheduler, web

Extension pointssettings includes · extension signalstask-source registry

CI-enforcedboundary:importsblocks enterprise imports

trueppm-enterprise · proprietary, separate repo

Portfolio governancecross-program views

Org identitySAML · SCIM · LDAP

Integration huborg-wide connectors

Audit and approvalstrail, workflows

Arrows run from Enterprise to the Community extension points and never the other way; the dashed CI-enforced check fails the build if the core imports from trueppm_enterprise.

The community edition must never import from trueppm_enterprise. The dependency is strictly one-way: enterprise → core.

Terminal window
# Verify the boundary is clean
make enterprise-boundary-check # OK: no trueppm-enterprise imports or dependency entries in packages.

A plain grep -r "trueppm_enterprise" packages/ is not the check. The tree legitimately names the package in extension-point docstrings and ADR pointers — that grep returns prose-only hits on a clean tree. The gate matches import syntax and quoted module paths, and ignores comments (#2603).

Community: scheduling engine, CPM, Monte Carlo, Schedule (Gantt-style) UI, Board, Sprints workspace, program management (coordinating multiple projects within a program), baseline comparison, offline sync, real-time, 5-role RBAC, REST/WS API, Helm chart, MS Project import/export. Also in the Community edition since 0.4: basic single sign-on (OIDC/OAuth login against your own identity provider), time tracking with a weekly timesheet, and in-app baseline capture. Also in the Community edition: the integrations (Jira import, a personal Jira source, GitLab/GitHub task links, Git-event automation, outbound webhooks), the read-only MCP server, the operational audit log, and read-only share links. Still on the Community roadmap: the installable PWA lands in 0.5, which is the mobile story through 1.0; no native app is scheduled.

Enterprise (separate repo): portfolio analytics and health scores, cross-program resource leveling, org identity governance (SAML 2.0 federation, SCIM provisioning, LDAP/AD directory sync, enforced org-wide SSO), immutable audit trail, custom roles, approval workflows, the org-wide Jira/GitLab/ServiceNow integration hub, AI scheduling, cross-program and portfolio scenario modeling, multi-tenancy.

The OSS unit is the program (one PM, one or more related projects). The Enterprise unit is the portfolio (multiple programs under organizational governance).

The API is one Django app per domain under packages/api/src/trueppm_api/apps/. The edges between those apps are governed by a declared layering, not by convention.

packages/api/app-layering.toml assigns every app to a layer, lowest first:

  1. foundation: idempotency, taskruns.
  2. core (lateral): access, profiles, teams, workspace, projects, notifications, scheduling, resources, timetracking, sync. These are mutually coupled by nature (one task write touches RBAC, scheduling, sync and notifications), so imports among them are allowed.
  3. satellite (lateral): agents, csvimport, jiraimport, msproject, integrations, webhooks, history, sso, workflow_engine.
  4. reporting: observability.

An app may import an app in a lower layer, or in the same layer when that layer is declared lateral. It may also import the shared platform modules (core, fields, permissions, workflows). It may not import a higher layer, and a platform module may not import an app. Composition roots (settings, urls, asgi, routing, celery) wire every app together by design and are not checked.

The gate, scripts/check-app-layering.py, counts every import statement (including function-local and TYPE_CHECKING imports) and every string constant that is wholly a dotted trueppm_api.* module path, such as an include("...") target. Migrations are skipped. It is a ratchet: the violations that existed when the gate was added are recorded in packages/api/app-layering-baseline.txt, a ceiling that can only shrink, and any import beyond it fails. The baseline total is printed on every run. The recorded violations are mostly the core and platform reaching up: access to agents, integrations and webhooks; projects to agents, integrations, webhooks and the importers; platform modules to apps; and several apps to observability.

  • Run it locally with make app-layering-check. It also runs in make pre-push and as the api:app-layering CI job.
  • Fix a violation by moving the shared code down a layer, or by inverting the dependency so the higher layer registers against a hook the lower layer owns. Then run python3 scripts/check-app-layering.py --update-baseline to lock the improvement in. That command refuses to add or raise an entry.
  • The ratchet is count-based, so it has two honest limits. A new edge always fails, but within an existing edge a site that was fixed and not yet locked in leaves slack that a new violation on the same edge can reuse; every run prints that slack with the command that locks it in. And two MRs can each pass alone yet red the merged tree (one removes a baselined site, the other removes the same one and adds another); rebase onto origin/main and re-run.
  • Editing the baseline file by hand to raise a count is caught: the gate compares it with the merge-base copy and fails unless the edge has a # raise-ok: <reason> comment on the line directly above it, which a reviewer sees in the diff. The marker counts only while it is new relative to the merge-base copy of the baseline, and --update-baseline drops it once the edge is no longer above the base count. It is still a self-grant written in the file it guards, a rubber stamp that removes the silence rather than preventing a wrong answer, exactly like # layering-ok:. The comparison fails closed when the CI diff base cannot be read, and is skipped, with a printed note, only in a local clone with no origin/main.
  • The gate reads tracked Python files only, so gitignored leftovers do not affect it. A new app must be git added before the gate sees it, and tracked .py files in an apps/<x>/ with no __init__.py are an error rather than silently skipped.
  • A deliberate exception carries # layering-ok: <reason> on the import or in the comment block directly above it (a blank line ends the block). The reason is required, and a bare marker fails on any line of a scanned file. The number of opted-out sites is printed on every run.
  • Adding an app directory fails the gate until the app is assigned a layer in app-layering.toml.

The gate reads import statements and whole-string module paths. It does not see:

  • module paths built at runtime: f-strings, concatenation, or importlib.import_module(variable);
  • from trueppm_api import apps followed by attribute access such as apps.projects.models;
  • model references by label: apps.get_model("projects.Task") and ForeignKey("projects.Task");
  • which names an import pulls in, so importing a constant counts the same as importing a model;
  • imports of a composition root (for example trueppm_api.celery), which are ignored by design;
  • test code, which legitimately crosses domains.