Django Integration

trueppm-scheduler has no Django dependency and is consumed as a plain Python library. The integration pattern is: service layer builds data classes → calls schedule() → writes results back to the database.

Terminal window
pip install trueppm-scheduler

1. Translate Django models to scheduler data classes

Section titled “1. Translate Django models to scheduler data classes”

The scheduler never touches the ORM. Write a translation function in your scheduling/services.py:

scheduling/services.py
from trueppm_scheduler import (
Calendar, DateRange, Dependency, DependencyType,
Project as SchedulerProject, Task as SchedulerTask,
ScheduleResult, schedule,
)
from .models import Project, Task # your Django models
def build_scheduler_project(django_project: Project) -> SchedulerProject:
"""Serialize a Django Project to the pure-Python scheduler representation."""
cal = django_project.calendar
scheduler_cal = Calendar(
working_days=cal.working_days,
hours_per_day=cal.hours_per_day,
timezone=cal.timezone,
exceptions=[
DateRange(start=exc.start_date, end=exc.end_date)
for exc in cal.exceptions.all()
],
)
tasks = [
SchedulerTask(
id=str(t.pk),
name=t.name,
duration=t.duration,
optimistic_duration=t.optimistic_duration,
most_likely_duration=t.most_likely_duration,
pessimistic_duration=t.pessimistic_duration,
)
for t in django_project.tasks.all()
]
deps = []
for d in django_project.dependencies.select_related("predecessor", "successor"):
deps.append(Dependency(
predecessor_id=str(d.predecessor_id),
successor_id=str(d.successor_id),
dep_type=DependencyType(d.dep_type),
lag=d.lag,
))
return SchedulerProject(
id=str(django_project.pk),
name=django_project.name,
start_date=django_project.start_date,
tasks=tasks,
dependencies=deps,
calendar=scheduler_cal,
)
def apply_schedule_result(django_project: Project, result: ScheduleResult) -> None:
"""Write CPM results back to the database in bulk."""
from django.db import transaction
task_map = {str(t.id): t for t in django_project.tasks.all()}
updates = []
for sched_task in result.tasks:
db_task = task_map.get(sched_task.id)
if db_task is None:
continue
db_task.early_start = sched_task.early_start
db_task.early_finish = sched_task.early_finish
db_task.late_start = sched_task.late_start
db_task.late_finish = sched_task.late_finish
db_task.total_float = sched_task.total_float
db_task.is_critical = sched_task.is_critical
updates.append(db_task)
with transaction.atomic():
Task.objects.bulk_update(
updates,
["early_start", "early_finish", "late_start", "late_finish",
"total_float", "is_critical"],
)
django_project.project_finish = result.project_finish
django_project.save(update_fields=["project_finish"])

Always dispatch scheduling work asynchronously. Use the transactional outbox pattern so that the Celery task is never dispatched before its triggering DB change is committed:

scheduling/tasks.py
from celery import shared_task
from django.db import transaction
from .services import apply_schedule_result, build_scheduler_project
from .models import Project
from trueppm_scheduler import schedule
@shared_task(bind=True, max_retries=3, default_retry_delay=5)
def recalculate_schedule(self, project_id: str) -> None:
"""Recompute CPM for the given project."""
try:
project = Project.objects.select_related("calendar").get(pk=project_id)
except Project.DoesNotExist:
return # project deleted between dispatch and execution — ignore
scheduler_project = build_scheduler_project(project)
result = schedule(scheduler_project)
apply_schedule_result(project, result)
# In your view or signal handler — dispatch on commit:
def enqueue_recalculate(project_id: str) -> None:
"""Dispatch a schedule recalculation after the current transaction commits."""
transaction.on_commit(
lambda: recalculate_schedule.delay(str(project_id))
)

Wire enqueue_recalculate to your task update view:

tasks/views.py
from rest_framework.viewsets import ModelViewSet
from scheduling.tasks import enqueue_recalculate
class TaskViewSet(ModelViewSet):
def perform_update(self, serializer):
instance = serializer.save()
# Only fields that affect the CPM graph need a recalculation.
cpm_fields = {"duration", "early_start", "dependencies"}
if cpm_fields & set(serializer.validated_data):
enqueue_recalculate(project_id=instance.project_id)

See 03-calendar-aware.ipynb for a runnable example of building a Calendar object from database records.