Capacity preflight

The Resource Manager’s view of an active sprint, at-a-glance. A donut chart shows aggregate committed/capacity ratio; a scrollable list shows per-person commitments with avatar initials. Three color bands signal severity: under, at, or over capacity.

Step 3 (Capacity preflight) of the hybrid PM flow — Sarah’s veto surface. Catches contention at plan time before sprint execution starts.

  • Donut chart — aggregate ratio (committed_hours / available_hours), tinted by band:
    • under 90% → semantic-on-track
    • 90–100% → semantic-at-risk
    • over 100% → semantic-critical
  • Aggregate label{committed} / {capacity} hours committed · On track · {buffer} hours of buffer (or overrun when negative)
  • Per-person rows — initials avatar + name + {committed}/{capacity} text; over-allocated members get a red avatar tint

The per-person hours view answers “who is overcommitted?”. A team that plans in story points also needs “are we over the sprint’s points ceiling?”. When the sprint carries a capacity_points value, the panel adds a points-based read alongside the hours view:

  • Points chip{committed}/{capacity} pts · {pct}%, summing the story points of every task committed to the sprint. The chip turns red once committed_points exceeds the sprint’s capacity_points ceiling.
  • Plain-English footer — a one-line summary the whole team can read without parsing the donut: “Team is at 75% of capacity. 6 pts free.” (or “Team is 4 pts over capacity.” when over the ceiling).

Both are omitted entirely when no points ceiling is set — a sprint that plans in hours only never sees an empty or zero-valued points chip. The capacity_points ceiling is set on the Plan Sprint dialog and editable while the sprint is planned.

  • Route: /projects/:projectId/sprints (right column of the metrics row, top half)
MethodEndpointPurpose
GET/api/v1/sprints/{id}/capacity/Per-member committed/available hours + aggregate totals

The activate endpoint also surfaces a warnings-only slice via capacity_check; this endpoint exposes the broader dataset.

For each TaskResource assigned to a task in the sprint:

committed_hours = sum(units × working_days × hours_per_day)
available_hours = max_units × working_days × hours_per_day

Working days span the sprint window honoring the project calendar’s working_days bitmask. Hours-per-day is read from the calendar (8.0 default).

PTO is a placeholder zero until a dedicated time-off model lands.

  • Sarah (Resource Manager) — this is your veto surface. If the aggregate is over 100% before activate, escalate before the sprint starts.
  • Maya (Scrum Master) — the per-person list answers “who’s overcommitted?” without a separate spreadsheet. The points footer (0.3) gives you the one-line “are we over the ceiling?” answer to read out at planning.
  • Raj (PM) — capacity warnings on activate inform whether to pull scope before the sprint window opens.