Capacity preflight

The Resource Manager’s view of an active sprint, at-a-glance. A donut chart shows aggregate committed/capacity ratio; a scrollable list shows per-person commitments with avatar initials. Three colour bands signal severity: under, at, or over capacity.

Step 3 (Capacity preflight) of the hybrid PM flow — Sarah’s veto surface. Catches contention at plan time before sprint execution starts.

  • Donut chart — aggregate ratio (committed_hours / available_hours), tinted by band:
    • under 90% → semantic-on-track
    • 90–100% → semantic-at-risk
    • over 100% → semantic-critical
  • Aggregate label{committed} / {capacity} hours committed · On track · {buffer} hours of buffer (or overrun when negative)
  • Per-person rows — initials avatar + name + {committed}/{capacity} text; over-allocated members get a red avatar tint
  • Route: /projects/:projectId/sprints (right column of the metrics row, top half)
MethodEndpointPurpose
GET/api/v1/sprints/{id}/capacity/Per-member committed/available hours + aggregate totals

The activate endpoint also surfaces a warnings-only slice via capacity_check; this endpoint exposes the broader dataset.

For each TaskResource assigned to a task in the sprint:

committed_hours = sum(units × working_days × hours_per_day)
available_hours = max_units × working_days × hours_per_day

Working days span the sprint window honouring the project calendar’s working_days bitmask. Hours-per-day is read from the calendar (8.0 default).

PTO is a placeholder zero until a dedicated time-off model lands.

  • Sarah (Resource Manager) — this is your veto surface. If the aggregate is over 100% before activate, escalate before the sprint starts.
  • Maya (Scrum Master) — the per-person list answers “who’s overcommitted?” without a separate spreadsheet.
  • Raj (PM) — capacity warnings on activate inform whether to pull scope before the sprint window opens.