Working Calendars

A project’s working calendar — its working days, hours per day, timezone, and holiday/shutdown exceptions — can be set at the workspace and program scope, not just per project. A value set higher inherits down to every program and project below it, where a Program Manager or Project Manager (or above) can override it for that scope. This page explains how the Workspace → Program → Project inheritance model resolves the calendar that actually schedules a project, who may override it, and how a calendar change ripples through the schedule.

For what a calendar itself contains — working days, hours per day, timezone, holiday exceptions, and how multiple calendars compose as overlays on one project — see Calendars. This page is about which calendar applies at a given scope, not what a calendar contains.

ScopeFieldWhat it controls
WorkspacecalendarThe default calendar for every program and project in the workspace that has no override.
ProgramcalendarOverrides the workspace default for every project in the program that has no override of its own.
ProjectcalendarOverrides the program (or workspace) default for that one project. Unchanged from today — this is the calendar a project has always carried.

Leaving a scope’s calendar unset (null) means “inherit” — it is not the same as “no calendar.” A project, program, or workspace that sets no calendar of its own always resolves to something, down to the system default described below.

The effective calendar — the one CPM actually schedules against — is resolved on the server and returned to every client (web, mobile, API), so no client re-implements the precedence. The chain is:

Workspace calendar → Program override → Project override
(the default) (optional) (optional)

Precedence — most specific wins:

  1. If the project sets an explicit calendar, that calendar applies.
  2. Otherwise, if the project’s program sets an explicit calendar, that calendar applies.
  3. Otherwise, the workspace calendar applies.
  4. If nothing in the chain sets a calendar, the system default applies: Monday–Friday, 8 hours/day, UTC.

A standalone project (one not in a program) inherits directly from the workspace. A program inherits directly from the workspace; a project in that program inherits the program’s resolved calendar. The system default is a code-level fallback, not a calendar record — no “System Default” calendar is created in your calendar library.

In the community edition, the parent value is a default, not a ceiling. A program or project may override the inherited calendar with a different one even when the workspace (or program) sets its own — swap in a four-day week for one project even though the workspace runs Monday–Friday. (The Enterprise Enforce policy changes this; see Locking the workspace calendar.)

Each program or project stores its calendar assignment as a nullable field:

  • No calendar set → the scope inherits the resolved parent calendar. This is the default for every new program and project.
  • Calendar set → the scope uses that calendar, regardless of the parent.

Choosing Inherit on the settings page clears the override and the scope falls back to the parent’s resolved calendar. The settings page shows an “Inherited from {scope}” indicator naming where the current calendar actually comes from — which may be the program, the workspace, or the system default — and overriding is presented as a first-class, equal choice, not a warning-worthy exception.

CPM, Monte Carlo, the program schedule view, and MS Project export all schedule a project against its one resolved effective calendar — there is only ever one precedence computation, in one place on the server, so every consumer agrees.

Changing a calendar at the workspace or program level is not just a settings edit: it automatically reschedules every project that inherits it. Reassigning the workspace calendar recomputes every project in the workspace that has no program or project override; reassigning a program’s calendar recomputes that program’s non-overriding projects. Recomputes are dispatched asynchronously through the existing scheduling queue, so a large workspace change enqueues many jobs rather than blocking the request that made it.

A project’s own calendar overlays (holiday and shutdown calendars applied on top) are a separate, orthogonal mechanism — inheritance picks the base calendar; overlays still compose on top of whichever base resolves.

Locking the workspace calendar (Enterprise)

Section titled “Locking the workspace calendar (Enterprise)”

The workspace carries a calendar override policy (calendar_override_policy) with three values:

  • Suggest (the default) — the workspace calendar pre-fills new programs and projects, but any scope can override it.
  • Inherit — every program and project follows the workspace calendar; the per-scope calendar picker renders read-only.
  • Enforce — the workspace calendar is mandatory and cannot be overridden below it.
ActionRequired role
View the resolved calendarAny member of the scope
Change the workspace calendarWorkspace Owner / Admin
Override a program’s calendarProgram Admin (or higher)
Override a project’s calendarProject Admin (or higher)
Create, edit, or delete a calendar in the shared libraryWorkspace Owner / Admin

Members, Schedulers, and Viewers see the resulting schedule but cannot change which calendar produced it.

The last row is about a calendar’s contents — its working days, hours per day, and holiday exceptions — rather than about which calendar a scope points at. It is deliberately the same role as the first row: a shared calendar’s working days feed the critical path of every project bound to it, so editing one moves finish dates across projects the editor may not even be a member of. A Project Manager can still point their own project at a different calendar (row four); what they cannot do is rewrite a calendar that other people’s plans also schedule against.

Reading the library is open to any signed-in user, so a Project Manager choosing an override can always see what is available.

Open Settings → Working calendar at the scope you want to configure:

  • Workspace — the root default for the whole workspace. Also carries the override policy above.
  • Program — overrides the workspace for every project in the program that inherits. Shows “Inherited from workspace ({name})” when no override is set.
  • Project — overrides the program (or workspace) for that one project. General → Working calendar shows the true resolved source, which may now be the project’s program rather than the workspace.

The resolved calendar and the scope it came from are exposed as read-only facts on the Project and Program API — first-class, additive fields so an agent or integration reads the effective calendar without re-implementing the precedence chain itself:

FieldWhereMeaning
effective_calendarProject, ProgramThe resolved calendar that actually applies at this scope.
calendar_sourceProject, ProgramWhere the effective calendar came from: project, program, workspace, or system_default.
inherited_calendarProgramThe calendar the program would use if its own calendar override were cleared — what drives the “Inherited from workspace” indicator.

The writable calendar field on Project, Program, and Workspace is unchanged in shape — this is an additive, non-breaking change. Existing projects that already set an explicit calendar are unaffected: their resolved calendar is byte-identical to before this feature.

See also Calendars for what a calendar contains and how overlays compose, Sharing & Access Inheritance and Attachment Policy for the same Workspace → Program → Project inheritance model applied to other settings, and Workspace Settings and Project Settings for the rest of each scope’s settings pages.