Recurring tasks

Recurring tasks let you repeat a task on a calendar cadence — a daily standup, a weekly safety walk, a monthly steering review — without hand-creating each instance. You configure the cadence once on a template task, and TruePPM spawns the upcoming occurrences for you.

The defining rule: a recurring task never enters the schedule’s CPM compute. A recurrence is a parallel, calendar-driven activity, not a node in the project’s logical network. A 365-occurrence daily standup has no business swamping the critical path, float, or the Monte Carlo P50/P80/P95 forecast — so recurring templates and every occurrence they generate are excluded from the scheduling engine entirely.

Open a task’s detail drawer and expand the Recurrence section. A task that doesn’t repeat shows an Add recurrence button (visible to Resource Manager and above — see permissions). The setup panel has:

FieldWhat it does
RepeatsDaily, Weekly, Monthly, or Custom
EveryThe interval — “every 2 weeks”, “every 3 months”. Custom is “every N days”.
OnWeekly only: which weekdays the task repeats on
Day of monthMonthly only: the day (1–31; clamped to the month length, so 31 still fires in February)
TimeTime of day and an IANA timezone
EndsNever, On a date, or After N occurrences

As you edit, a Next 4 occurrences preview updates live so you can see exactly when the task will land before you save. A banner reminds you the task is excluded from the critical path and Monte Carlo while it recurs.

Click Save recurrence to attach the rule. The task immediately leaves the CPM graph and the schedule recomputes without it; Stop recurring detaches the rule (existing occurrences are kept) and the task rejoins the schedule.

Per-occurrence inheritance is controlled by toggles on the rule:

  • Inherit assignees — each occurrence is assigned to the same person as the template.
  • Inherit attachments — the template’s attachments are copied onto each occurrence (referencing the same stored file, not a duplicated upload).
  • Inherit subtasks and Notify assignees the morning of are shown but labeled “Not active yet” — they are stored on the rule for a future release and have no effect today.

Occurrences are generated lazily, not all at once. An hourly job materializes only the occurrences due within a look-ahead window (TRUEPPM_RECURRENCE_HORIZON_DAYS, default 14 days) — a never-ending daily rule never creates an unbounded backlog of rows. Each generated occurrence is an ordinary task (status Not started), flagged as recurring so it stays out of the schedule, and is not placed in the WBS.

Reading a task’s recurrence is open to any project member. Creating, editing, or stopping a recurrence requires Resource Manager or above — the same gate as editing dependencies, because attaching or detaching a rule changes what the scheduler computes. Members see a read-only summary of the rule.

Recurring tasks vs. subtasks vs. child tasks

Section titled “Recurring tasks vs. subtasks vs. child tasks”
MechanismCPM participationUse when
Recurring taskNo — excluded entirelyThe work repeats on a calendar cadence (ceremonies, recurring reviews)
SubtasksNo — the parent is the CPM nodeInternal checklist for a single deliverable
Child tasks under a phaseYesThe items need sequencing, separate resourcing, or Gantt visibility