Cost model

This page is for project managers who need to know what a project has cost so far and whether it is running over budget, and for workspace admins who set the rates that cost is computed from.

TruePPM computes cost from data you already keep:

  • the budget you set on a project,
  • the hourly rate on each resource, and
  • the time entries people log against the project’s tasks.

Nothing is entered twice. A contributor logs time the way they always have, and the cost follows from it.

When 0.5 lands, the budget, rates and currency are set through the API, as shown below, and the program overview shows the rolled-up cost KPIs. Screens for editing rates and budgets come with a later cost UI.

InputWhere it livesWho can set itWho can see it
Budget (budget at completion, BAC)ProjectProject Manager (project Admin) or OwnerProject Manager or Owner
Hourly rateResourceWorkspace Admin or OwnerWorkspace Admin or Owner. A Project Manager also sees the rate of each person who logged time on their project, in that project’s cost breakdown.
CurrencyWorkspace settingsWorkspace Admin or OwnerEveryone

A rate is a stand-in for what a person costs the organization, so it is never shown to a Member or a Viewer. That holds everywhere a rate or a cost figure could travel: the resource catalog, the project roster, the project’s activity history, exports, share links, agent (MCP) reads, and the program rollup. In the program rollup, the cost KPIs show a number only to someone who is Program Manager or Owner on the program and Project Manager or Owner on every project in it. Everyone else sees Restricted to managers of every project.

Each resource has one current rate. There is no rate history, and no rate takes effect from a date. Actual cost is always computed at the rate as it is now, so changing a rate re-costs every hour that resource has ever logged, including last month’s.

That is deliberate, and it is why every rate change goes through a preview first (see Changing a rate). Date-effective rate cards, where a new rate applies only from a given date, are an enterprise-edition feature.

A rate of 0 is a real rate, for a volunteer or a donated resource, and counts as set. A resource with no rate is unrated.

Rates belong to resources, not user accounts, so equipment and other non-human resources can carry one too. Only people log time, so only people produce cost. Non-labor costs such as equipment, cloud spend and agent spend are planned for a later release.

All amounts are in the workspace currency. Set it with the currency field on PATCH /api/v1/workspace/ (workspace admins), as a three-letter ISO 4217 code, for example USD, EUR or GBP. The default is USD. It is a label, not a converter: changing it re-labels every existing amount and converts nothing.

FigureFormula
Actual cost (AC)For each person who logged time on the project: hours × the current hourly rate of their resource, summed
Percent completeThe project’s existing percent complete: the average percent complete of its tasks
Earned value (EV)budget × percent complete ÷ 100
Cost variance (CV)EV − AC. Negative means over budget
Budget utilizationAC ÷ budget. 1.0 (100 %) means the whole budget has been spent

Example: a project has a budget of 10,000 and is 50 % complete, so EV is 5,000. Two people have logged 11.5 h at 100/h and 0.75 h at 80.50/h, so AC is 1,150.00 + 60.38 = 1,210.38. CV is 5,000 − 1,210.38 = 3,789.62 (under budget), and utilization is 12 %.

Each line is rounded to the cent and the lines are then added together, so the breakdown always adds up to the total.

What counts as actual cost:

  • Only time logged on this project’s tasks. Time a person logs on another project belongs to that project.
  • Time off is never cost. Holidays and PTO are calendar exceptions, not time entries.
  • A running timer is not cost until it is stopped and becomes a time entry.
  • Deleted time entries do not count. Time logged on a task that was later deleted still counts, because the money was spent.
  • A deactivated resource still prices its past hours. Off-boarding someone does not erase what their work cost.

When a person has more than one resource, TruePPM uses the one on the project’s team roster. When a person’s account is not linked to any resource, TruePPM uses a resource with no linked account and the same email address.

A cost figure that is missing an input says which input is missing instead of showing a misleading number.

What you seeWhyWhat to do
N projects have no budgetA project, or one of the program’s projects, has no budget, or a budget of 0A Project Manager sets budget on the project with PATCH /api/v1/projects/{id}/
N people have no rateSomeone who logged time on the project, or who is assigned to one of its tasks, has no rate. Their hours cannot be pricedA workspace admin sets each person’s rate with POST /api/v1/resources/{id}/rate/. This works for a deactivated resource too. If the person has no resource at all (their entry in the breakdown has no resource_id), first create one with their email address (POST /api/v1/resources/), then rate it. TruePPM matches a resource with no linked account to the person by email
Restricted to managers of every projectYou are not Program Manager or above on the program, or not Project Manager or above on every project in itNothing; cost is restricted

Actual cost is still shown while rates are missing, but it covers only the priced hours. The cost breakdown lists the unpriced hours and names the people who have no rate.

Project Managers can read a project’s cost at GET /api/v1/projects/{id}/cost/. The response returns:

  • the budget, actual cost, percent complete and earned value
  • cost variance and budget utilization, each with a reason when it cannot be computed
  • cost_computable, which is false when anyone in scope has no rate, and missing_rate_count
  • the people with no rate
  • logged, priced and unpriced hours
  • one line per person: hours, rate and cost
  • a one-sentence definition of every figure

Amounts are decimal strings in the workspace currency.

Workspace admins set rates with POST /api/v1/resources/{id}/rate/, with a body of {"cost_rate": "85.00", "dry_run": true}. The same endpoint handles the preview and the save:

  • with dry_run: true (the default), it returns what every affected project’s actual cost would become, without saving anything;
  • with dry_run: false, it saves the rate and returns the same shape, recomputed from the saved data.

The preview and the save use the same computation, so the numbers you approve are the numbers you get. Each affected project shows its hours, actual cost before and after, the change, and whether its cost is computable before and after. Set cost_rate to null to clear a rate.

Saving records a Resource rate changed entry in the workspace audit log, with the old and new rate. Saving the rate a resource already has records nothing.

A rate can only be changed from a signed-in session, not with an API token, because a change re-costs history. Sending cost_rate on PATCH /api/v1/resources/{id}/ is rejected with a pointer to this endpoint.

An assistant connected through the MCP server reads the same breakdown with the read-only get_project_cost tool. It returns the payload described above, including definitions, cost_computable and missing_rate_count.

Below Project Manager the tool answers cost_restricted with a reason and no figure; it never returns a budget, rate or cost value, and it is not an error.

Parity commitment. Every cost figure the web app shows is reachable through an MCP tool: the project breakdown through get_project_cost, and the program rollup’s cost KPIs through get_program_health, which returns the rollup, cost KPIs included. A cost figure added to the UI without an MCP route is a gap to be filed, not an accepted difference.

When cost data is complete, the program rollup’s two cost KPIs compute as program totals:

  • Cost variance is the sum of every project’s CV.
  • Budget utilization is total actual cost ÷ total budget. A large project counts in proportion to its budget; small projects do not each count equally.

Both are unavailable if any project in the program is missing a budget or a rate, because a partial total would understate the program. The tile names how many projects or people are missing.

The Budget-weighted aggregation policy weights each project by its budget. If any project has no budget, the rollup uses the average instead and says why. Budget weighting is applied only for someone who may see every project’s budget, under the same rule as the cost KPIs, because a weighted figure reveals how the budgets compare. Everyone else sees the plain average, with a note that budget weighting is unavailable.

A project that has spent hours but has no remaining tasks earns nothing, so its percent complete is 0 and its whole actual cost shows as negative cost variance. See Program rollup KPIs.