Subtasks

Subtasks are a checklist-style decomposition of a single task. They live inside a task’s detail drawer, carry their own assignee and status, and roll up into the parent task’s progress — but they are not independently scheduled. The CPM engine treats the parent task as the scheduling unit; subtasks are the implementer’s internal breakdown of how to complete it.

Why subtasks exist alongside child tasks under a phase

Section titled “Why subtasks exist alongside child tasks under a phase”

TruePPM has two ways to break work down:

MechanismCreated viaCPM participationUse when
Child tasks under a phaseGantt indent (Tab key / context menu)Yes — each task gets its own duration, float, dependencies, resource assignmentsThe sub-items need to be sequenced, separately resourced, or tracked on the Gantt
SubtasksTask detail drawerNo — the parent task is the CPM nodeThe sub-items are the assignee’s to-do list for a single deliverable

The practical test: if any of the sub-items could end up on the critical path, or if a PM needs to see them on the Gantt, make them child tasks under a phase. If they’re internal steps that only the task owner cares about, use subtasks.

A task called “Write requirements document” might have subtasks:

  • Draft stakeholder interview questions
  • Conduct interviews
  • Write first draft
  • Circulate for review
  • Incorporate feedback

None of these need their own Gantt bar. The PM cares only that “Write requirements document” finishes by Friday. The subtasks are the author’s own workflow for getting there.

If, on the other hand, the work is “Design → Build → Test”, those belong as three separate tasks under a phase — they have distinct durations, different assignees, and a Finish-to-Start dependency chain the scheduler needs to know about.

Subtasks are one level deep. A subtask cannot have its own subtasks. This keeps the data model and the UI predictable — there is no unlimited nesting that gradually becomes an unmaintainable tree.

The parent task’s % complete is the weighted average of its subtasks’ progress. Completing all subtasks brings the parent to 100%. If the parent has no subtasks, progress is set directly on the parent as normal.

Each subtask has its own assignee. Subtasks assigned to you appear in My Tasks with a label showing the parent task name so you always have context.

If a subtask is added to a task that belongs to an active sprint, TruePPM records a scope-change event on the sprint. Sprint leads can see what subtasks were added mid-sprint and by whom, supporting the kind of transparency a Scrum team needs for retrospectives and velocity accuracy.

Subtasks appear in board columns by default (they have status and assignee). Use the Hide subtasks toggle in the board filter bar to declutter the board view if your team prefers to work at the task level only.

Subtasks are hidden from the Gantt by default. The parent task renders as a summary bar with a subtask count badge. Expanding the parent inlines the subtask bars as indented leaf rows beneath it.

SituationRecommendation
Breaking a sprint story into developer to-dosSubtasks
Decomposing a deliverable into steps only the assignee tracksSubtasks
Work that has separate owners, durations, or deadlinesChild tasks under a phase
Items that must be sequenced with Finish-to-Start dependenciesChild tasks under a phase
Items a PM wants visible on the GanttChild tasks under a phase
A QA checklist inside a “QA” taskSubtasks
Separate “Design”, “Build”, “Test” workstreamsChild tasks under a phase