Velocity calibration

This is for PMs on a hybrid team, where the schedule’s duration estimates and the team’s own velocity — points completed per sprint — can drift apart. When a sprint closes, TruePPM looks at the team’s rolling six-sprint velocity (points completed per working day) and, for each task in the closing sprint that has story points (the team’s own size estimate) set, suggests a more realistic duration for the schedule. The suggestion appears in the task’s detail drawer, in the Estimates section, as a “Revise estimate from Sprint N?” banner. The PM accepts or dismisses it; the estimate is never changed without that explicit choice.

This is the agile → CPM half of the hybrid PM bridge — sprint reality feeding back into the Monte Carlo forecast.

After Step 6 (Execute — daily cadence, two worlds in sync) closes a sprint, the next CPM recompute carries the team’s actual delivery rate forward into the forecast.

  • Banner in the Task Detail Drawer (Estimates section) when a pending suggestion exists:

    📈 Revise estimate from Sprint 12? Team velocity suggests 4d for this task (currently 2d). [Dismiss] [Accept]

  • Accept writes the new duration onto the task and re-runs the schedule (CPM — the calculation that works out each task’s dates from durations and dependencies — plus a Monte Carlo forecast) so the plan reflects the calibrated estimate immediately.

  • Dismiss records the PM’s decision audit-trail-style; the task estimate is untouched and no further prompts arrive for that (task, sprint) pair.

  • The banner is PM-only (role ≥ Project Manager). Lower roles never see it — TruePPM does not surface CPM language to the delivery team.

A VelocitySuggestion row is created when all of the following hold:

  1. A sprint has just transitioned to COMPLETED (via the sprint close drain).
  2. The project has at least three prior completed sprints. Below that threshold the rolling average is too noisy to trust; no suggestion appears.
  3. Rolling team velocity is non-zero. A zero-velocity team produces an undefined duration, so suggestions are skipped until the team has delivered something.
  4. The task has story points set, and the suggested duration is actually different from its current estimate (no point prompting the PM to accept the value already in place).

The formula is:

team_velocity_per_day = mean(completed_points / sprint_working_days) # last 6 closed sprints
suggested_duration = round(task.story_points / team_velocity_per_day)

A single working day is the minimum — a suggestion of zero is clamped to 1.

Governance — the project’s estimation mode

Section titled “Governance — the project’s estimation mode”

When the project’s estimation mode is set to Suggest & approve, a suggestion is flagged for review before it can be accepted. In the PM only and Open modes, the PM can accept it directly. Either way, the estimate is never changed silently — accepting is always an explicit choice.

MethodEndpointPurpose
GET/api/v1/velocity-suggestions/?task={id}&pending=trueList pending suggestions for a task
POST/api/v1/velocity-suggestions/{id}/accept/Write most_likely_duration and enqueue CPM recompute (PM only)
POST/api/v1/velocity-suggestions/{id}/dismiss/Audit-only dismissal (PM only)
GET/api/v1/projects/{id}/velocity/Now also includes team_velocity_per_day for the project

accept is idempotent on an already-accepted suggestion. Re-accepting after dismiss (or vice versa) returns HTTP 409 to preserve the original decision.

  • ADR-0065 — Hybrid Bridge v1.1 (velocity feedback, “My Work”, inbound sync)
  • ADR-0032 — Three-point estimates (the input that velocity calibrates)
  • ADR-0037 — Sprint model and close drain
  • Sarah (PM) — read the banner when it appears. Accept when the team’s pace genuinely differs from the original estimate; dismiss when the difference is a one-off (Black-Friday-week noise, a contractor onboarding, etc.). Either way, your decision is preserved in the audit trail.
  • Alex (Scrum Master) — you don’t see this surface. Sprint reality is yours; CPM calibration is the PM’s.
  • Janet (Exec) — calibrated estimates feed Monte Carlo, which feeds your portfolio forecast. The honesty of the forecast depends on the PM keeping up with these suggestions.