Schedule dates

Every task on the Schedule has a Start and a Finish, but they do not all come from the same place. Two dates are in play, and only one of them is yours:

FieldWho sets itWhat it means
Committed startplanned_startYou (the PM)“This work is not to begin before this date”
Computed startscheduled_startThe CPM pass”Given the network (and, once work has begun, reality), when this task’s work spans from”

The Start column shows the computed date, because that is the one the schedule actually runs on. A committed start does not replace it — it constrains it.

A committed start is a start-no-earlier-than (SNET) constraint. On each forward pass the engine takes the later of the two:

early_start = max(computed early_start, committed start, project start)

So it is a floor, not a pin. Committing 12 May does not hold the task on 12 May — it stops the task from drifting earlier than 12 May. A predecessor that slips will still push the task past it, and that is correct: a constraint that overrode the network would be a way of hiding a late plan rather than seeing one.

Two consequences worth knowing:

  • A task can be uncommitted and still anchored. A schedulable task assigned to a sprint inherits its sprint start date as a synthetic floor, so agile work positions inside its sprint window instead of sliding back to the project origin. That floor is engine input only — nothing is written to the task, and the task still reads as having no committed start.
  • Committing a start is not the same as setting a deadline. There is no finish-side constraint yet — planned_finish is reserved and the engine does not read it. The constraint set TruePPM intends to adopt is recorded in ADR-1049 (proposed); see Scheduling before the project start for the related project-boundary behavior.

Committing a start that has already arrived

Section titled “Committing a start that has already arrived”

Committing a start on a To Do task sets more than the date when that date is today or earlier. A task whose committed start has arrived is underway, so TruePPM also moves it to In progress. If the date is in the past, the task’s actual start is recorded as that day too.

Every control that can trigger it says so before you click — the drawer’s Set committed start, and the unscheduled gutter’s quick actions and Promote to schedule. Each gains a clause naming the status change, and the confirmation after the write repeats what actually happened. A future date changes nothing but the date, and the controls read as they always have.

“Already arrived” is judged against the server’s date, not your browser’s. On a team spread across time zones the two can disagree by a day, and it is the server that decides.

To commit a past start without moving the task out of To Do, set the status back to To Do after committing — the promote only fires on the write that sets the date.

Why a task in progress with no committed start is flagged

Section titled “Why a task in progress with no committed start is flagged”

A task that has reached In progress, Review, or Complete without a committed start carries an amber no committed start chip on its Schedule row, and the same advisory inside the task detail drawer.

The flag is not about the task being late. It is about the dates being unfalsifiable. Work is underway, so somebody made a real-world decision to begin — but nothing on the task records what that decision was, so its Start and Finish are pure CPM output that will move every time a predecessor moves. There is no baseline to have been wrong about, and nothing to compare a slip against. That is the specific case where “computed” stops being a harmless default and starts costing you the ability to tell a plan from a rewrite of the plan.

Summary tasks are excluded — their dates are rollups of their children, not a committed start of their own.

The chip offers exactly two remediations, because there are exactly two honest answers:

  • Set committed start — accepts the CPM-computed start as the committed one. Use this when the task genuinely started when the schedule said it would; you are confirming the plan, not changing it. From here on, the date is a record, and later movement is visible as movement.
  • Move to To Do — returns the task to Not started. Use this when the status was the mistake — the card was dragged early, or work was expected to begin and did not.

Pick by asking what actually happened in the world, not which one makes the chip go away.

Not every task needs a committed start, and committing every task is its own failure mode — a schedule where every task carries a floor is a schedule that can no longer compress, and the critical path stops telling you anything. Leave a task on computed dates when its timing is genuinely derived: routine work in the middle of a chain, tasks whose only real constraint is their predecessor, anything not yet started.

Commit a start when there is a reason outside the network — a vendor arrives that week, a gate is fixed, the work has begun. Those are the dates worth defending; the rest should be free to move.

Once a task is in progress, the schedule engine tracks two related but different quantities, and the Schedule view is careful to keep them visually separate:

  • The bar (and the Start/Finish columns) show the task’s span — where its work began (scheduled_start) through where it finishes (early_finish/scheduled_finish — the two are always the same date). The bar keeps its full planned length as work progresses; a fill grows inside it left-to-right as % complete rises, the same convention MS Project and most Gantt tools use.
  • early_start (an engine-internal field, not shown on this view) is different: it names the remaining-work window — where the task’s unfinished work would need to start, laid forward from today, to hit the same finish. For a task that hasn’t started, or one that’s finished, the two windows are identical. For a task in progress they diverge, and the divergence is informative: a 4-day task that’s 83% done has roughly a day of remaining-work window left, even though its span — when the work actually began — may have started days or weeks ago.

Before this distinction existed, the bar was drawn from the remaining-work window instead of the span. The visible effect was a bar that shrank as progress was logged, rather than filling — a 4-day task at 83% rendered as a single day, indistinguishable from someone having cut the estimate. The span is what fixes that: the bar’s length now reflects the real commitment, and the fill is the only thing that moves as work advances.

The task detail drawer’s Duration cell carries the same idea in numeric form: the full estimate (4d) stays put, and a “1d left” qualifier chip appears beside it once work is underway and the remaining window has shrunk below the estimate — a property of the duration, not a second, disagreeing date. A task that hasn’t started, or one that’s complete, shows no chip: there is nothing left to qualify.

One consequence worth knowing: when a task’s actual start is on record and work has run long, its span can end up longer than its estimated duration — an eleven-day span against a four-day estimate, say. That is not a bug. It is the visible form of work taking longer than planned, and it is exactly the situation the span exists to surface rather than hide.

The project start date is the floor for the schedule: the critical-path engine does not plan a task to begin before it, with one exception described below. But the floor is elastic in the earlier direction. When you place a task on a date before the project start — by typing a date, creating the task, importing from MS Project, or writing through the API — TruePPM keeps the floor honest by pulling the project start back to fit the task, in the same change. The task lands where you put it, and the project boundary follows; nothing is silently clamped or discarded.

Only the earlier direction is automatic. Moving the project start later (past tasks that already begin before the new date) stays a deliberate Project Settings edit. Pulling the start earlier to fit a task needs only the permission to edit that task — the project boundary is treated as a derived artifact of its tasks — so it isn’t gated behind project administration, and collaborators see the new start update in real time.

Because this lives at the API layer, every write path behaves the same way, including integrations and imports that set task dates directly.

The one exception is a task whose links are all Start-to-Finish. An SF link can require its successor to finish before the predecessor starts. If that predecessor opens the project, the successor belongs before the project start, and the engine puts it there. The project start date itself does not move. Only the task’s computed dates sit ahead of it, and the Schedule draws the bar there. MS Project schedules the same case the same way. The data date still applies: remaining work is never scheduled before it. When a project has no status date, the data date is today. As a result, you see this placement only when the SF anchor falls on or after the data date, for example in a project that starts in the future.

Two consequences to know about:

  • Adding a non-SF link restores the floor. The exception covers only a task whose links are all SF. If you add an FS, SS or FF link to such a task, it returns to the project start, even when the new link would allow an earlier date on its own. Adding a link can therefore move a task later. This is tracked in #4220.
  • Rescheduling the task by hand opens the before-project-start prompt. Dragging or nudging an SF-placed task that sits before the project start asks you to move the project start or snap the task to it. Both options override the SF placement. This is tracked in #4221.

See Scheduler conventions for the exact rule.

The server owns every scheduled date. When you drag a bar or pick a milestone date, the view shows your value immediately so the plan keeps up with you — but the authoritative date comes back from the CPM pass, and it can differ. The engine applies the project’s real working calendar, including holiday exceptions the browser never receives; a span you drop next to a shutdown week will land somewhere you did not predict.

That difference is always shown, never applied silently:

  • A date you have just authored renders in italic until the server confirms it.
  • If the server lands on a different date, the row keeps a → new date marker and the value it replaced. The marker stays until you acknowledge it — you are never asked to spot the change yourself. Widen the Start or Finish column and the marker also shows the old date struck through.
  • A strip above the forecast bar reports “N dates changed” and announces the recomputation to screen readers. Show N changes filters the outline down to just the changed rows; Acknowledge all clears the markers.
  • A change the server refuses — permission, a lock, a validation error — is listed with the reason it gave and a Retry. It is never reverted without explanation.

The marker states the change as a fact — “Finish moved Oct 13 → Oct 16” — and adds a reason only where one can be proven from the project’s work week (“Oct 13 is not a working day”). When the move came from a holiday, a dependency cascade, or a constraint, the strip says what changed but not why: the browser is not told the cause, and a plausible-sounding guess would be worse than silence. To see why a specific date moved, open the task’s change history.

Only dates you authored are marked. A teammate’s edit arriving over the live channel updates the plan as it always has — see Real-time collaboration.

You do not have to drop a bar to find out what it costs. While a drag or a keyboard reschedule is live, TruePPM paints preview bars — translucent ghosts on every downstream task the move would shift, with a red frame and a CP badge on any task the move puts onto the critical path. This works in both directions: pulling a bar earlier shows the successors it pulls in with it, and the milestone readout reports a date that moves closer just as it reports one that slips. Work that has actually started stays where it started, and a task with a committed start no earlier than date is never pulled back through it.

A corner label reads “Preview — server confirms on drop”, because this is a browser-side estimate on a plain Monday–Friday week: it does not know the project’s holiday exceptions or a custom calendar, so near a shutdown week it can be several days out, and the CPM pass on drop is what decides. At most ten ghosts are drawn at once; beyond that a +N more affected count tells you the blast radius is larger than what is on screen. Press Esc to back out with nothing changed.

A bar whose dates come from recorded actuals will not move. Once a task is complete and carries a recorded actual start or finish, the scheduling engine takes it out of network logic entirely — its actuals are the truth, and the planned start is never consulted for it again. You can still grab such a bar, and the drag says so while you hold it: “Recorded actuals set this task’s dates — the drop won’t move it.” Completion alone does not do this. A task marked 100% with no recorded actuals is still scheduled by the network and drags normally; it is the actuals, not the checkbox, that pin the dates. To move a pinned task, change its actual dates in the task drawer’s Actual dates section — see Recording and correcting actual dates.

The keyboard path draws the same line. Pressing r (or Shift+Enter) on a pinned task does not start a reschedule, and says why — the same sentence the drag shows, announced to a screen reader. A task complete with no recorded actuals starts a keyboard reschedule normally, exactly as it drags normally.

Actual dates are the record of what happened, as opposed to the plan. TruePPM stamps them for you on the transitions where the date is unambiguous, and gives you one place to correct them when it got the date wrong — which it will, because people update the board on Monday for work they finished on Friday.

TransitionWhat is recorded
→ In progressActual start = today, if none is on record yet
→ In reviewActual finish = today, if none is on record yet
→ CompleteActual finish = today, if none is on record yet
In review ⇄ CompleteNothing changes — the recorded finish is kept
Reopened out of In review or CompleteActual finish is cleared

Two things about this table are deliberate and worth stating plainly, because both look like omissions.

Nothing ever invents an actual start. A card taken straight to done without ever passing through In progress has no start date to record, and stamping today would collapse its bar to a single day. TruePPM leaves the field empty instead and lets the scheduling engine derive the historical span backward from the finish. A task with a finish and no start is a correct, complete record — not a gap to fill.

In review records a finish; Complete does not overwrite it. “In review” means the work is done and awaiting sign-off, so the finish date is known at that moment. Sign-off can come days later, and the date that matters is when the work finished, not when somebody got round to approving it.

That second rule is the one that changes what a contributor’s completion is worth. Marking a task 100% moves it to In review, and before 0.4 that path recorded no actual dates at all — so the highest-volume way work gets completed produced no record of when it happened.

Open the task drawer and expand Actual dates on the Details tab. Both fields are ordinary date pickers; each change saves immediately and re-runs the schedule, because an actual date moves where the task sits on the timeline.

Three rules apply, and TruePPM will tell you which one you hit:

  • Actual start cannot be later than actual finish. Editing either field is checked against whatever the other one currently holds.
  • Neither date can be in the future. The ceiling is the project’s data date when that is set ahead of today, otherwise today.
  • Actual finish can only be set on a task that is in review or complete. On a task still in progress the field is present but inert, and says so. This is not bureaucracy: the scheduling engine reads a recorded finish as “this task is done” and pins the task’s dates to it, so a finish on a running task would show the work as complete on the timeline while the board still shows it in flight. Moving the task and setting the date in the same edit is fine — it is only a bare finish date on a running task that is refused.

If you can view a project but not edit it, the section shows the recorded dates as plain text.

There is no dialog on any completion path. Marking a task complete inline, dragging a card to Done, and bulk-completing a selection all behave exactly as they did — none of them stops to ask you for dates. The drawer is the correction path, and it is somewhere you go on purpose.