AI-native by design
If you are evaluating TruePPM as the system an AI agent reads from and writes to, this page is the one to read first. It ties together five architectural facts that are documented individually elsewhere and explains why, together, they make TruePPM a trustworthy foundation for agentic project management — rather than one more project database with a chatbot bolted on.
The short version is a single principle: computed, not guessed. An agent should never be the thing that decides your critical path or your P80 date. It should ask the engine, and the engine — deterministic, versioned, self-hosted — should answer. Everything below is in service of that.
The problem this design avoids
Section titled “The problem this design avoids”Every incumbent PPM tool is bolting a large language model onto a project database and letting the model answer scheduling questions directly. That fails in a specific, predictable way: LLMs are strong at extracting intent from unstructured text and weak at graph traversal, date arithmetic, and constraint propagation — exactly the math a schedule is made of. Ask a model “if this task slips three days, when do we ship?” and it will produce a confident, plausible, and frequently wrong date, with no derivation you can check.
TruePPM takes the opposite stance. The model’s only job is to translate — turn your question into an engine call, and phrase the engine’s answer back in natural language. The number itself always comes from the deterministic engine. Five architectural properties make that division of labor real.
1. A discoverable API surface — OpenAPI 3.0.3
Section titled “1. A discoverable API surface — OpenAPI 3.0.3”Every feature in TruePPM is a REST or WebSocket endpoint before it is a UI element (API-first). The web and mobile clients are API consumers with no privileged access — an agent gets the same surface they do.
That surface is described by an OpenAPI 3.0.3 schema served at /api/schema/,
the authoritative contract for projects, tasks, dependencies, resources, sprints,
risks, and the rest of the domain. Because modern agent frameworks consume OpenAPI
directly for tool discovery and function calling, an agent can learn how to read
and (eventually) mutate a TruePPM instance from the schema alone — no bespoke
integration code. See the API stability contract for what is
versioned and safe to build against.
2. A first-class entry point — the read-only MCP server
Section titled “2. A first-class entry point — the read-only MCP server”An OpenAPI schema tells an agent how to call the API. The read-only MCP
server (trueppm-mcp) gives it a curated, safe place to
start. It shipped in 0.4 as the beta headliner: point any Model Context
Protocol client — Claude Desktop, Cursor, Zed —
at your self-hosted instance and ask real questions of the live schedule.
The server will expose a focused set of read-only tools — critical path, a
non-mutating Monte Carlo what-if, sprint status, the risk register, My Work — each
mapping to one existing endpoint and returning only what the caller’s role already
permits. It runs as a local subprocess next to your client, talks to TruePPM only
over HTTPS with a scoped mcp:read token, and touches no database directly. The
step-by-step client setup lives in Connect your MCP
client.
3. The anti-hallucination substrate — a deterministic engine
Section titled “3. The anti-hallucination substrate — a deterministic engine”This is the property that makes the whole design defensible. TruePPM’s Critical
Path Method and Monte Carlo risk analysis live in a standalone, deterministic
package — trueppm-scheduler,
published to PyPI and independent of Django. It handles all four dependency
types, lead/lag on every link, cycle detection, and P50/P80/P95 forecasts (see
Monte Carlo forecasting). A second Rust + petgraph
CPM implementation (packages/wasm-scheduler) is validated against it by a
shared conformance fixture suite in CI; today that Rust engine is a conformance
reference only — the web client’s drag preview runs a calendar-approximate
TypeScript worker, reconciled by the authoritative server CPM on commit, and
wiring the WASM build into the browser for in-browser and offline recompute is
future work (#1777).
Because the engine is deterministic and separable, the same inputs always produce the same schedule, and that schedule can be validated without a running database or a running model. An agent extracts intent — from a meeting transcript, an email, a prompt — and hands structured tasks and dependencies to the engine; the engine computes the timeline. The agent never does the math, so the agent can never hallucinate the math. That is what computed, not guessed means in practice.
4. Answers you can cite — the provenance graph
Section titled “4. Answers you can cite — the provenance graph”A computed answer is only trustworthy if you can see why. The provenance graph (#1058), the first piece of the AI-native foundation, shipped with the 0.4 MCP server: every computed date, float, and P80 carries the server-side derivation that produced it — the driving constraint, the lag, the calendar contribution, the critical chain behind a percentile.
Over MCP this surfaces as a dedicated derivation tool, so an agent’s answer can be “P80 is October 22, derived from this critical chain” rather than a bare assertion. Provenance is what turns computed, not guessed from a slogan into something auditable: the number arrives with its reasoning attached, and a human — or another agent — can check it.
5. Your data stays yours — self-hosted and Apache 2.0
Section titled “5. Your data stays yours — self-hosted and Apache 2.0”The single biggest blocker to AI in enterprise PPM is data residency: organizations will not ship proprietary timelines, resourcing, and forecasts to a third-party SaaS. TruePPM’s community edition is Apache 2.0 and deploys on your own infrastructure via Docker Compose or the Helm chart.
That makes a fully private agent loop possible: run TruePPM and a local model on your own hardware, point the MCP server at localhost, and no plan and no inference ever leaves your box. The natural-language query layer and bring-your-own local-model adapter (#1060, #1061, planned for 0.5) extend this — the model translates locally, the engine answers locally.
Human-in-the-loop is the default
Section titled “Human-in-the-loop is the default”TruePPM’s data model already prefers suggestion over override. Sprint velocity, for example, feeds non-destructive suggestions into CPM durations rather than silently rewriting the plan (see velocity calibration). This is the right shape for AI: an agent proposes an adjustment with its derivation, and a person clicks approve or reject. The plan is never mutated behind the practitioner’s back.
What is OSS and what is Enterprise
Section titled “What is OSS and what is Enterprise”The AI story splits cleanly along the same line as the rest of TruePPM: a team’s own AI capability is OSS; org-level AI governance is Enterprise.
| Capability | Edition | Status |
|---|---|---|
| OpenAPI 3.0.3 contract, API-first surface | Community (OSS) | Shipped |
Deterministic engine (trueppm-scheduler on PyPI; Rust/WASM conformance reference, not yet browser-wired) | Community (OSS) | Shipped |
| Read-only MCP server + provenance (query the schedule) | Community (OSS) | Shipped in 0.4 |
Agent-action audit foundation — hash-chained record + audit_verify (the reproduce substrate; ADR-0112 Accepted) | Community (OSS) | Landed in 0.4 |
| Natural-language query layer, local-model adapter | Community (OSS) | Planned for 0.5 |
| MCP write surface (create/update task, move card, log time), engine-as-referee safe writes | Community (OSS) | Planned for 0.6 |
| Reproducible answers (engine-version + input hash) | Community (OSS) | Planned for 0.9 |
| AI scheduling, cross-program and portfolio scenario modeling, cross-program agents, audited automation, approval workflows | Enterprise | — |
The dividing question is the same one the whole product uses: would a single PM or team need this to run their program? Reading and eventually writing your own schedule with an agent — OSS. Governing what agents may do across many programs, with an org-wide audit trail and approval gates — Enterprise.
The refusal generalization — named, not yet proven
Section titled “The refusal generalization — named, not yet proven”Everything above grounds one domain: scheduling feasibility. The open architectural
question is whether the same verdict → refusal → audit path can ground a second,
non-scheduling domain — a budget cliff, a DORA control, a data-residency rule — behind a
domain-agnostic Invariant → Verdict registry, without the pipeline knowing anything about
tasks or baselines.
That registry is a backlog item to prove, not a shipped abstraction. It is tracked as the
instance-#2 experiment on the roadmap: express one concrete
non-scheduling control as an Invariant, run it through the existing refusal and agent-action
audit path, and confirm it refuses-with-derivation and writes a clean audit entry. If it
factors cleanly, TruePPM grounds more than schedules; until it does, we describe TruePPM as
grounding scheduling, not as a general “grounding engine.” The compliance framing that rides
on this — why a deterministic refusal is an effective challenge to probabilistic agent
behavior (SR 11-7) — lives on the Computed, not guessed
page, out of the practitioner’s way.
Where to go next
Section titled “Where to go next”- Computed, not guessed — the architectural commitment behind this page, and its full roadmap sequencing.
- MCP server (read-only) — the tool surface, security posture, and edition boundary in detail.
- Connect your MCP client — mint a token and wire up Claude Desktop, Cursor, or Zed.
- Monte Carlo forecasting — the risk engine an agent queries for P50/P80/P95.
- Roadmap — the source of record for what has shipped versus what is planned.