MS Project configuration
This page is the operator’s reference for TruePPM’s MS Project import / export surface. The user-facing flows ship with sensible defaults — most deployments do not need to change anything here — but the four knobs below cover upload size, the optional .mpp toolchain, history retention, and what’s enforced on parsed input.
Upload size cap
Section titled “Upload size cap”The per-file import cap defaults to 50 MB and is set by the MSPROJECT_MAX_UPLOAD_MB environment variable.
| Setting | Default | Unit | What it bounds |
|---|---|---|---|
MSPROJECT_MAX_UPLOAD_MB | 50 | megabytes | Maximum file size accepted by the import endpoints (.xml and .mpp). Files larger than this are rejected with HTTP 400 before any parsing happens. |
The cap is deliberately lower than the 100 MB attachment ceiling. An import is read fully into memory and stored base64-encoded in a single ImportRequest database row (~33% inflation), so a 50 MB upload already costs ~67 MB of RAM and row size during the import window. 50 MB is also the practical MS Project file ceiling — schedules larger than that degrade in MS Project itself.
Setting it lower is safe — TruePPM will reject larger uploads with a clear error message naming the configured cap.
.mpp and Java
Section titled “.mpp and Java”The .xml (MSPDI) format is parsed by TruePPM directly and always works — no Java dependency. Binary .mpp files need the optional MPXJ command-line JAR and a Java 11+ runtime.
| Setting | Default | Notes |
|---|---|---|
MPXJ_JAR_PATH | /opt/mpxj/mpxj-cli.jar | Path to the MPXJ CLI JAR inside the API container. Set via a Django settings override only — an environment-variable binding is not yet wired. |
If a user uploads a .mpp and the JAR isn’t at the configured path, the import fails with ".mpp import is not available on this server (reference <id>). Contact your administrator." The expected JAR path and the MPXJ_JAR_PATH hint are logged server-side (msproject.mpxj_jar_missing error_id=<id>), not shown to the user. Conversion failures likewise log JVM stderr under msproject.mpxj_failed error_id=<id>. The user-facing import dialog and the format picker both recommend “File → Save As → XML Format” in MS Project as the workaround — .xml round-trips with everything .mpp round-trips, with the exception of MS Project’s binary-only formatting / view state (which TruePPM never reads anyway).
The reference TruePPM Docker image does not bundle the MPXJ JAR or a JRE. To enable .mpp import on a self-hosted deployment, you have two options:
- Build a custom API image that installs OpenJDK 11+ and downloads the MPXJ CLI JAR into
/opt/mpxj/. This is the cleanest path for production. - Mount the JAR via a Helm value-supplied volume and add a Java sidecar or init-installer. Heavier setup; usually only worth it if you cannot rebuild images.
Helm values are not currently pre-wired for either. Because MPXJ_JAR_PATH is read from Django settings (not the environment), override it in a settings module baked into your custom image — for example a trueppm_api.settings.custom module that imports the prod settings and sets MPXJ_JAR_PATH = "/opt/mpxj/mpxj-cli.jar", selected via DJANGO_SETTINGS_MODULE. The default path already matches option 1 above, so a custom image that installs the JAR at /opt/mpxj/mpxj-cli.jar needs no override at all.
The subprocess timeout for MPXJ conversion is fixed at 120 seconds. A timed-out conversion marks the ImportRequest row DEAD and reports a clear error in the import summary.
Import history retention
Section titled “Import history retention”After every import attempt — successful or failed — TruePPM persists an ImportRequest row that powers the project history section on each project Overview and the GET /projects/{pk}/imports/ endpoint.
| Setting | Default | Unit | What it bounds |
|---|---|---|---|
TRUEPPM_IMPORT_RETENTION_DAYS | 7 | days | How long an ImportRequest row (and its uploaded file content) is kept after the import reaches a terminal state. Older rows are removed by the retention purge coordinator (default daily at 02:00 UTC — see Retention). |
Two reasons to consider tuning this:
- Lower — you have a privacy or storage constraint and don’t want uploaded file contents lingering. The minimum useful value is
1(one full day, so an end-of-day import is still visible the next morning);0disables retention entirely and is not recommended (it strips the surface that makes a failed import recoverable). - Higher — you want longer ad-hoc visibility of who imported what. Up to ~30 days is reasonable; beyond that, build durable audit on top of the enterprise audit overlay, which consumes the
history_record_createdsignal rather than relying on the outbox row.
Keep in mind that the file_content_b64 column stores the entire uploaded file (base64-encoded). A 50 MB upload retained for 30 days under churn can grow the table fast; if you raise this setting, watch table size.
What’s enforced on parsed input
Section titled “What’s enforced on parsed input”Two boundaries protect the API container from a hostile upload, independent of the size cap:
- XML entity expansion is disabled. All MSPDI parsing goes through
defusedxml, which refuses entity declarations and external-entity resolution. A “billion laughs” or XXE payload is rejected at parse time. This is a hard guarantee — there is no setting to relax it. Verified bytests/apps/msproject/test_parser_security.py. - Parsed
Durationvalues are clamped to the model’sMaxValueValidator(36_525)(~100 years). A crafted file encodingPT9999999999Hwould otherwise smuggle astronomical integers past the bulk-create path (which skips Django field validators). The clamp is in the parser helper, so it covers the primaryDurationfield and the three PERTDuration1–Duration3values uniformly.
Both protections are unit-tested and are not opt-out. They exist because the import surface is project-admin authenticated, not public — but project admin is not a security-sensitive role and the file content is user-supplied, so the parser treats every byte as hostile.
Quick reference
Section titled “Quick reference”# Common production values; all four below have safe defaultsMSPROJECT_MAX_UPLOAD_MB=50 # defaultTRUEPPM_IMPORT_RETENTION_DAYS=7 # default# MPXJ_JAR_PATH defaults to /opt/mpxj/mpxj-cli.jar — Django settings override# only (no env-var binding); only matters if you support .mpp# (no env var) defusedxml + duration clamp are unconditionalSee MS Project import & export for the user-facing guide; Configuration for the full TruePPM environment-variable reference.