Program risk policy
This is for a program manager who wants to control what happens when a delay in one project threatens another. When one project’s task is a predecessor for a task in another project in the same program, a slip in the first can block the second. The Program Settings → Risk & deps policy page decides what the program does when that happens. Open it at Program → Settings → Risk & deps policy.
The page has three parts:
- A read-only 5×5 risk matrix showing the Workspace-wide probability × impact thresholds.
- A cross-project dependency slip policy — the main control on this page.
- An auto-escalate after day count.
This is intra-program only. The policy governs dependencies between projects inside the same program. Cross-program and portfolio coordination is out of scope — that is an Enterprise concern.
Permissions
Section titled “Permissions”| Action | Minimum role |
|---|---|
| View the risk policy | Program Viewer |
| Change the slip policy or escalation days | Program Manager |
A program Viewer sees the page in read-only mode. Only a Program Manager or above can change the slip policy or the escalation window.
The risk matrix is read-only here
Section titled “The risk matrix is read-only here”The 5×5 matrix (probability 1–5 × impact 1–5, scored low / medium / high / critical) is shown for reference but cannot be edited on this page. The thresholds are Workspace-wide, not per-program, so they are managed elsewhere and rendered here read-only so program admins can see the scale their slip policy operates against.
Slip propagation
Section titled “Slip propagation”This is the core decision: what the program does when a predecessor task in one project slips and blocks a successor in another. There are three rungs, which let a PM step up enforcement as a program matures.
| Policy | Identifier | Behavior |
|---|---|---|
| No action | none | The slip is visible in the schedule, but no notification or gate fires. A deliberate opt-out. |
| Warn only (default) | warn | Notifies the successor PM and the program manager via an in-app alert. The successor task is not blocked. |
| Block & escalate | block | Locks the successor task from starting and opens an escalation ticket. The strongest enforcement. |
warn is the default because it matches how the program overview already renders a slip indicator: the overview surfaces the slip, and warn adds an in-app alert to the people involved without gating work. none and block are explicit opt-outs in either direction — silence the alert, or harden it into a gate.
Escalation days
Section titled “Escalation days”The Auto-escalate after value is the number of days a blocked dependency can sit without resolution before it escalates to the program manager. It must be an integer between 1 and 30; the default is 3. Values outside that range are rejected (the page surfaces the error inline before you can save).
How escalation interacts with the slip indicator
Section titled “How escalation interacts with the slip indicator”The slip indicator on the program overview surfaces a cross-project dependency slip as soon as it is detected. Escalation days govern how long that slipped dependency may remain unresolved before it is escalated to the program manager:
- Under Warn only, the slip indicator appears and the successor PM and program manager get an in-app alert immediately. If the dependency is still unresolved after the escalation window, it escalates to the program manager.
- Under Block & escalate, the successor task is locked and an escalation ticket opens; the escalation window bounds how long that blocked state persists before the escalation is raised to the program manager.
- Under No action, nothing escalates — the slip is only visible in the schedule, so the escalation window has no effect.
The slip indicator answers “has something slipped?”; the escalation days answer “how long before we raise it?”
The slip policy and the escalation days are edited together and saved together via the settings save bar.
Why can’t I edit the risk matrix here? The probability/impact thresholds are Workspace-wide so that risk scores mean the same thing across every program. They are shown here read-only as the reference scale; editing them is a separate, Workspace-level concern.
Does the slip policy apply across programs? No. It applies only to dependencies between projects within the same program. Cross-program coordination is an Enterprise capability and is out of scope for this page.
What happens at exactly the escalation-day boundary? Escalation fires once a blocked dependency has been unresolved for the configured number of days. Set it lower to escalate sooner, higher to give teams more room to resolve a slip before the program manager is pulled in. The allowed range is 1–30 days.
What is the API behind this page?
GET and PATCH /api/v1/programs/{program_id}/risk-policy/, returning slip_propagation (none / warn / block) and escalation_days (1–30). Reads require program Viewer; writes require Program Manager or above. Both fields are validated server-side.