trueppm-scheduler has no Django dependency and is consumed as a plain Python library. The integration pattern is: service layer builds data classes → calls schedule() → writes results back to the database.

Terminal window
pip install trueppm-scheduler

1. Translate Django models to scheduler data classes

Section titled “1. Translate Django models to scheduler data classes”

The scheduler never touches the ORM. Write a translation function in your scheduling/services.py:

scheduling/services.py
from datetime import date
from trueppm_scheduler import (
Calendar, DateRange, DeliveryMode, Dependency, DependencyType,
Project as SchedulerProject, Task as SchedulerTask,
ScheduleResult, schedule,
)
from .models import Project, Task # your Django models
def _to_scheduler_calendar(cal) -> Calendar:
return Calendar(
working_days=cal.working_days,
# hours_per_day and timezone are reserved-but-inert: the engine schedules
# in whole-day units only, so these two fields are carried for API/model
# parity but do not change any computed date. Pass your real values
# anyway (round-tripping matters if you serialize the Calendar back out).
hours_per_day=cal.hours_per_day,
timezone=cal.timezone,
exceptions=[
DateRange(start=exc.start_date, end=exc.end_date)
for exc in cal.exceptions.all()
],
)
def build_scheduler_project(django_project: Project) -> SchedulerProject:
"""Serialize a Django Project to the pure-Python scheduler representation.
Passes every recorded input the engine reads: progress and actuals, the
start-no-earlier-than date, the status (data) date, per-task calendars, and
the agile inputs. Leave one out and the schedule silently ignores it.
"""
scheduler_cal = _to_scheduler_calendar(django_project.calendar)
db_tasks = list(django_project.tasks.select_related("calendar"))
# Per-task calendars: register each distinct calendar under its id. A task's
# calendar_id must have an entry here, or the engine refuses the project with
# InvalidScheduleInput rather than scheduling it on the project calendar.
calendars = {
str(t.calendar_id): _to_scheduler_calendar(t.calendar)
for t in db_tasks
if t.calendar_id is not None
}
tasks = [
SchedulerTask(
id=str(t.pk),
name=t.name,
duration=t.duration,
optimistic_duration=t.optimistic_duration,
most_likely_duration=t.most_likely_duration,
pessimistic_duration=t.pessimistic_duration,
# Progress (ADR-0132): percent_complete is 0-100. A task with an
# actual_finish is pinned to its recorded dates, not rescheduled.
percent_complete=t.percent_complete,
actual_start=t.actual_start,
actual_finish=t.actual_finish,
# Start-no-earlier-than constraint.
planned_start=t.planned_start,
calendar_id=str(t.calendar_id) if t.calendar_id is not None else None,
# Agile-aware Monte Carlo inputs (None means waterfall).
delivery_mode=DeliveryMode(t.delivery_mode) if t.delivery_mode else None,
story_points=t.story_points,
# Hand back the milestone edge the previous run persisted. The engine
# reads it only on a completed milestone; it is ignored on any other
# task, and None is always safe.
live_day_end_on=t.early_finish if t.milestone_at_day_end else None,
)
for t in db_tasks
]
deps = []
for d in django_project.dependencies.select_related("predecessor", "successor"):
deps.append(Dependency(
predecessor_id=str(d.predecessor_id),
successor_id=str(d.successor_id),
dep_type=DependencyType(d.dep_type),
lag=d.lag,
))
return SchedulerProject(
id=str(django_project.pk),
name=django_project.name,
start_date=django_project.start_date,
tasks=tasks,
dependencies=deps,
calendar=scheduler_cal,
calendars=calendars or None,
# The data date: completed work is held fixed and remaining work is
# scheduled no earlier than this. The engine never reads the clock, so
# resolve a null status date to today here.
status_date=django_project.status_date or date.today(),
velocity_samples=django_project.velocity_samples,
sprint_length_days=django_project.sprint_length_days,
)
_RESULT_FIELDS = [
"early_start", "early_finish", "late_start", "late_finish",
"total_float", "free_float", "is_critical",
"scheduled_start", "milestone_at_day_end",
]
def apply_schedule_result(django_project: Project, result: ScheduleResult) -> None:
"""Write CPM results back to the database in bulk."""
from django.db import transaction
task_map = {str(t.id): t for t in django_project.tasks.all()}
updates = []
for sched_task in result.tasks:
db_task = task_map.get(sched_task.id)
if db_task is None:
continue
for name in _RESULT_FIELDS:
setattr(db_task, name, getattr(sched_task, name))
updates.append(db_task)
with transaction.atomic():
Task.objects.bulk_update(updates, _RESULT_FIELDS)
django_project.project_finish = result.project_finish
django_project.save(update_fields=["project_finish"])

Three of the persisted outputs are not decoration:

  • scheduled_start is the task’s whole span. For an in-progress task, early_start is only the remaining-work window, so draw bars from scheduled_start.
  • free_float is separate from total_float; persist both.
  • milestone_at_day_end says which edge of the shown day a milestone sits on. The end of a Friday and the start of the next Monday are the same point in working time, so two shown days must never be diffed as a slip. Persist it with early_finish, and build_scheduler_project() hands it back on the next run through live_day_end_on.

Always dispatch scheduling work asynchronously. Use the transactional outbox pattern so that the Celery task is never dispatched before its triggering DB change is committed:

scheduling/tasks.py
from celery import shared_task
from django.db import transaction
from .services import apply_schedule_result, build_scheduler_project
from .models import Project
from trueppm_scheduler import schedule
@shared_task(bind=True, max_retries=3, default_retry_delay=5)
def recalculate_schedule(self, project_id: str) -> None:
"""Recompute CPM for the given project."""
try:
project = Project.objects.select_related("calendar").get(pk=project_id)
except Project.DoesNotExist:
return # project deleted between dispatch and execution — ignore
scheduler_project = build_scheduler_project(project)
result = schedule(scheduler_project)
apply_schedule_result(project, result)
# In your view or signal handler — dispatch on commit:
def enqueue_recalculate(project_id: str) -> None:
"""Dispatch a schedule recalculation after the current transaction commits."""
transaction.on_commit(
lambda: recalculate_schedule.delay(str(project_id))
)

Wire enqueue_recalculate to your task update view:

tasks/views.py
from rest_framework.viewsets import ModelViewSet
from scheduling.tasks import enqueue_recalculate
class TaskViewSet(ModelViewSet):
def perform_update(self, serializer):
instance = serializer.save()
# Only fields that affect the CPM graph need a recalculation.
cpm_fields = {
"duration", "dependencies", "percent_complete", "planned_start",
"actual_start", "actual_finish", "calendar",
}
if cpm_fields & set(serializer.validated_data):
enqueue_recalculate(project_id=instance.project_id)

The guide also passes project-level inputs, so call enqueue_recalculate() from the project’s own update path whenever status_date, start_date or the project calendar change, not only from task updates.

See 03-calendar-aware.ipynb for a runnable example of building a Calendar object from database records.