Project templates

A template captures a project’s shape so the next project like it does not start from an empty outline.

What a template carries — and what it refuses to

Section titled “What a template carries — and what it refuses to”

This is the whole design, so it is worth stating as a table rather than burying in prose.

CarriedStripped
Phase / task treeOwners and assignees
Dependencies, with lag and typePlanned, actual and baseline dates
DurationsPercent complete and status
Milestones and gatesComments, files, time entries
Delivery modes (waterfall / scrum / kanban)Baselines
Sprint length

The right column is not a limitation, it is the point. A template applied in November must not schedule to the publisher’s March, and a user id from the publishing workspace is either unresolvable in yours or — worse — resolvable to the wrong person. Adopting a template can never import somebody else’s moment into your plan.

Durations are carried, because a duration is an estimate of effort: a property of the shape, not of when the shape ran.

Templates deliberately seed phases, gates, milestones and dependencies rather than sixty guessed task names. The working assumption is that teams delete most of what a template writes, and deleting is treated as a first-class act rather than a failure — see the seeded-row provenance that makes “delete untouched rows” computable.

If it turns out teams keep the detail, nothing is lost by having started small.

Every template in the gallery carries a chip:

ChipMeaning
WorkspacePublished for everyone in this workspace
CommunityPublished by someone else, shared into view
YoursYou published it

The chip is visible before adoption, because who published a skeleton is the first thing most delivery leads judge it by. Workspace and Community are stored on the template, so every reader sees the same answer; Yours is the one label resolved per reader, since it is the only one that is genuinely relative to who is asking.

Alongside the chip, each row states how many rows it will write and what it carries.

Pick a template in the new-project flow. Blank project is the default and a first-class choice, not an escape hatch.

Seeding runs in the background: the create sheet never blocks on it. TruePPM schedules the new rows against your calendar and start date as soon as they land — the dates never come from the template.

Applying a template requires the Project Manager role or above on the target project. Publishing one requires the same on the source project. Seeing the gallery needs only authentication — for a workspace-wide template. A template published from inside a program is offered only to that program’s members; everyone else’s gallery simply omits it.

For a waterfall or hybrid template, applying it lands you straight on the Schedule with the skeleton already scheduled, not on an empty Overview you have to leave to find it. An agile template lands on the Product Backlog the same way, with its epics and stories standing.

Because seeding runs in the background, the Schedule can be genuinely empty for a moment after you land on it. While the rows are still being written it shows a brief “Setting up your schedule…” skeleton instead of the ordinary empty state — so a project whose template is still applying never reads as one that failed to apply, and never invites you to type a first row into a plan that is about to be overwritten. The skeleton clears itself the moment the first rows arrive. The product backlog shows the matching “Setting up your backlog…” state for an agile template, and clears it the same way. An apply that genuinely does fail says so in as many words, on whichever surface you landed — see When an apply doesn’t finish below.

Once the rows have landed, a banner across the top states what just happened and gives you the fastest way to disagree with it:

  • What was written — the template’s name, and how many rows, milestones and dependencies it created, plus which calendar they were scheduled against.
  • Delete untouched rows (N) — a one-click sweep that removes every row the template wrote that nobody has looked at since. It only ever touches rows a machine wrote and a person hasn’t edited; the moment you rename, reschedule, or otherwise touch a row, it drops out of the count and is safe from the sweep. Requires Project Manager or above, and asks you to confirm before it runs.
  • Undo apply (⌘Z) — reverses the whole application in one step, same as described below.

Every seeded-and-untouched row also carries a small tick mark in the outline margin, so you can see at a glance which rows are still exactly as the template wrote them.

None of this is a commitment you have to act on. Dismiss the banner and keep working — the tick marks and the delete offer stay available for seven days after a row is seeded, whether or not you ever open the banner again.

Sometimes an apply fails — the template was deleted while the job sat in the queue, the project was archived after you asked for it, or the server hit an error part way through. The surface you landed on tells you — the Schedule for a waterfall or hybrid template, the Product Backlog for an agile one — instead of leaving you on an empty project wondering whether anything happened at all:

Couldn’t apply “House shape”. Nothing was written. This project is exactly as empty as it was before.

The second sentence is a guarantee, not a soft landing. Seeding runs inside a single database transaction, so a failure rolls the whole thing back: a template never lands half-applied, and there is nothing left behind to find, clean up, or undo. Beneath the headline the banner shows the server’s own reason, so you can tell this template no longer exists apart from the database was briefly unreachable.

You have three ways forward:

  • Try again re-applies the same template to the same project. It appears for Project Manager and above, and only while the template still exists — if it has since been deleted, the banner says so rather than offering a button that cannot work.
  • Keep the empty project. The ordinary blank schedule — or empty backlog — is right there under the banner with the first row waiting for you. Nothing was written, so this project is no different from any other new one.
  • Start again from a different template by creating a new project from the gallery. Applying a different template to a project that already exists is not something you can do yet.

Dismiss the banner with × once you have decided. It appears on phones too, above the “No items yet” card on the Schedule and the empty-backlog card on the Product Backlog.

Below the schedule, a second strip — separate from the banner — surfaces a few things worth doing, in plain language, derived from the plan itself rather than a fixed checklist:

  • rows nobody has assigned an owner to,
  • milestones nobody has confirmed since the template wrote them,
  • and phases that are not yet connected to the rest of the plan by any dependency.

Like the banner, none of this is required — it states so plainly — and it disappears entirely once there is nothing left worth flagging, rather than nagging about rows you have already looked at.

Undo is one step — and it keeps what you have typed

Section titled “Undo is one step — and it keeps what you have typed”

An application can be undone as a single step. It removes exactly the rows that application wrote — nothing that was already in the project, and nothing another application added.

It deliberately keeps any row somebody has since edited, and tells you how many it kept. Undoing a template five minutes after a teammate started filling in one of its rows must not take their work with it: leaving a row behind is disappointing, deleting a sentence somebody wrote is not recoverable.

Three starters ship with TruePPM, one per methodology, so the Template way in is never empty on a fresh install:

StarterMethodologyShape
Scrum product teamAgileDiscovery, then two sprints that build a walking skeleton before a real slice
Stage-gate deliveryWaterfallFive gated phases with a hold point at each
Regulated releaseHybridA gated validation branch beside a sprint-driven build branch

They carry a Bundled provenance chip and sort last in the gallery: on a workspace that has published its own shapes, those are the ones worth reading first.

They are deliberately small. A starter is a shape to argue with, not a plan — enough structure that the phases and the dependency spine are visible, few enough rows that deleting the half that does not apply is a minute’s work.

Project → Settings → Templates. The page opens on six counts — tasks, phases, gates, dependencies, milestones and methodology — computed by the server from the same extraction the publish itself runs, so the number you approve is the number that gets written.

Publishing needs Project Manager role on the source project. Everything a template would carry is already visible to any member in the Schedule; publishing is the only act that is gated.

The form asks for a name, a description and a methodology, then states — read only — what will and will not be carried. That inventory is not a set of toggles on purpose: per-publish “carries” switches produce templates that differ in invisible ways, and two templates with the same name that bring different things destroy the comparability templates exist for.

The methodology also decides where an adopting project lands: an Agile template opens on a seeded Product Backlog, not on a Schedule of dateless bars.

Below the inventory sits the card itself — the same card a delivery lead will meet in the gallery, rendered live from what you have typed. The choice your template actually faces is a side-by-side one against every other shape on the list, and a name that reads fine in a text field can still be the one nobody picks. The description is the only line that argues for it, which is why the field asks who the template is for rather than what it contains.

A name that is already taken comes back as a conflict, not a silent overwrite, and offers to publish the next version instead. The earlier version stays published and selectable, marked superseded.

That is deliberate. Projects already created from v1 are the only record of why they look the way they do, and a version edited underneath them turns that record into a lie.

Nobody is notified when you publish. A template is an option that appears, not an announcement — if the PMs should know, that is a message you send.

Frozen is the operative word: the template does not stay linked to the project it came from. Editing, archiving or deleting that project afterwards leaves every published template untouched — otherwise a skeleton two teams had already adopted could change under them, or vanish.

Deleting the source project clears the provenance line and leaves the template working.

A project can carry at most 2,000 rows into a template.

Once a template has been applied, Project → Settings → Template divergence states how the project has moved away from it. Four counts, over the rows the template wrote:

CountWhat it means
UnchangedStill exactly as the template wrote them — nobody has touched the row.
AdaptedSomeone on the project edited the row after it was seeded.
RemovedThe row was deleted after the template wrote it. (A row deleted long enough ago to have been purged by the tombstone sweep is no longer counted — there is nothing left to count.)
AddedRows in the project that no template wrote, including any that predate the adoption.

Above the counts is the provenance line — which template, which version, who applied it and when. That line survives the template being deleted: the name and version are recorded on the project’s adoption record, so “this came from Delivery Skeleton v3” outlives v3.

A project that was never created from a template says so, and reports nothing else.

The digest is symmetric — the team reads it first

Section titled “The digest is symmetric — the team reads it first”

The page is readable by every member of the project, Viewer included, and it is the same page for everyone. Project settings used to be admin-only end to end, so a Viewer or Team Member who opened it was redirected away; they now reach the page and see the sections that concern them, which today is this one. Everything else on the page stays admin-only, and the server still refuses their writes. There is no fuller version for a PMO, no second endpoint, and no audience parameter — a program manager looking at one project’s divergence and that project’s own team are reading the identical report.

That is not a courtesy. A report about a team’s decisions that the team cannot read is surveillance with better typography, so the team-side page ships first and the API has exactly one route for it.

Nothing on this page approves, rejects, queues, or scores anything. There is no compliance percentage, no health band, and no action that submits the project for review. Divergence is information, and adapting a template is the expected outcome — the parts a team changed are the parts that did not fit, which says as much about the template as about the project.

Templates are authorable centrally and adoptable locally. Hard enforcement is deliberately not here.