Jira import
This page is for a Project Manager bringing an existing Jira issue set into TruePPM as a real, schedulable plan. TruePPM can turn a Jira Server / Data Center issue export into a project the scheduling engine can compute dates for: upload the XML you get from Jira’s issue navigator, and TruePPM creates one task per issue, sets each task’s duration from its original estimate, and draws a Finish-to-Start dependency (the successor task can’t start until its predecessor finishes) for every Blocks link. The result is a real critical-path network — durations plus dependencies are exactly what the scheduling engine needs to compute dates.
This is the minimal “get real data in and computable” slice: enough to lift a Jira issue set into a schedule and see a critical path, not a full-fidelity Jira replica. See What does not map for the deliberate exclusions.
Import a file, or connect your account?
Section titled “Import a file, or connect your account?”Two separate Jira features shipped in 0.4, and they solve different problems. Pick by what you want at the end:
| Jira import (this page) | Jira personal pull | |
|---|---|---|
| What you get | Tasks in a TruePPM project | Your assigned Jira issues mirrored into My Work |
| Enters the schedule? | Yes — real tasks with durations and Finish-to-Start dependencies, scheduled by CPM | No — a read-only pointer; never enters CPM, sprints, the board, or your load |
| How it connects | An .xml file you upload; no connection to Jira | A live, authenticated connection to your own Jira account |
| Jira Cloud | Not supported — Cloud has no XML export | Supported, as well as Data Center / Server |
| Who sets it up | A Project Manager, once per file | You, for your own account |
| How it refreshes | It doesn’t. Importing the same issues again adds a second set of tasks rather than updating the first — the import-into-existing-project path is additive | Sync now, plus an automatic pull when you open My Work and the cached items have gone stale |
Use the import to lift a Jira issue set into a schedule you will manage in TruePPM. Use the personal pull to keep working in Jira while still seeing your Jira work beside your TruePPM tasks. They are independent — you can use either, both, or neither.
The personal pull is set up under Settings → Connected Accounts; see Connected Accounts for the connect wizard, the JQL and project filters, and what it does and does not mirror. It is read-only, one-way, and never writes back to Jira, and it is per-user — only you see your own items.
Export your issues from Jira (Server / Data Center)
Section titled “Export your issues from Jira (Server / Data Center)”Jira import reads the XML produced by Jira’s issue navigator — the format
that carries the <issuelinks> block, which is what makes the network
computable. (CSV does not include issue links, so it is not accepted.)
- In Jira, open the issue navigator and run the filter (or search) whose issues you want to import.
- Choose Export → XML (top-right of the navigator).
- Save the resulting
.xmlfile.
Import the file into a project (Project Manager or above)
Section titled “Import the file into a project (Project Manager or above)”Jira import lands issues into an existing project. Upload runs through the API described below; the import is enforced server-side to require the Project Manager role or above on the destination project — members below Project Manager cannot import.
The import runs asynchronously. A successful upload returns immediately with
an import_request_id; the worker parses the file, validates the derived graph,
persists the tasks and dependencies, and triggers a CPM recalculation in the
background. The schedule refreshes once the import finishes.
What maps
Section titled “What maps”| Jira export | TruePPM | Notes |
|---|---|---|
One <item> (issue) | one Task | Flat WBS — sequential top-level outline numbers, no hierarchy |
<summary> | Task.name | Falls back to the RSS <title> (key prefix stripped), then the bare issue key, so a task is never nameless |
<timeoriginalestimate seconds="…"> | Task.duration | Seconds → whole working days on an 8-hour day (see Duration mapping) |
<status> | Task.status and Task.percent_complete | Recognized status names only; a delivered issue arrives at 100% (see Status and progress mapping) |
Blocks issue link | Finish-to-Start Dependency | Both directions read (“blocks” and “is blocked by”); lag 0. See Dependency mapping |
<channel><title> | Project.name (on the import summary) | Used to label the imported set; falls back to “Imported from Jira” |
Duration mapping
Section titled “Duration mapping”Jira stores the original estimate in seconds. TruePPM converts to whole working days on an 8-hour day, rounding up to the next whole day and flooring at 1 — an issue with no estimate (or an unparseable one) still becomes a 1-day task, never zero-length. A zero-duration task is invisible to CPM float and critical-path math, which is the entire reason the importer reads estimates at all.
Jira timeoriginalestimate | Working days |
|---|---|
| (absent / unparseable) | 1 |
| 4 h (14 400 s) | 1 |
| 8 h (28 800 s) | 1 |
| 12 h (43 200 s) | 2 |
| 16 h (57 600 s) | 2 |
| 3 d @ 8 h (86 400 s) | 3 |
Status and progress mapping
Section titled “Status and progress mapping”An issue’s <status> name sets the imported task’s status, so work that is
already done or in flight does not arrive as unstarted future work and inflate
every forecast. The match is on the status name, case-insensitively:
| Jira status | TruePPM Task.status |
|---|---|
| Backlog | Backlog |
| To Do, Todo, Open, Reopened, Selected for Development | Not started |
| In Progress, In Development | In progress |
| In Review, Review, In Test | Review |
| Done, Closed, Resolved, Complete | Complete |
An issue whose status is not in that list — a customized workflow step such
as “Ready for QA” or “Deployed” — imports as Not started, and so does an
issue with no <status> element at all.
A Jira XML export carries no percent-complete field, so progress is derived from
the status alone: an issue that maps to Review or Complete arrives at
100%, and every other status arrives at 0%. Task.percent_complete is a
0–100 percent, and it is the same figure the progress ring, the Gantt fill and
the parent rollup read, so a delivered issue reads as delivered everywhere.
Dependency mapping
Section titled “Dependency mapping”Every Jira Blocks link becomes a Finish-to-Start dependency with lag 0. The link direction sets predecessor and successor:
- An outward “blocks” link makes the issue the predecessor (the blocker).
- An inward “is blocked by” link makes the issue the successor (the blocked issue).
Because both endpoints of a single link appear in the export, TruePPM normalizes and de-duplicates the two halves so a link is imported once. Only the Blocks link type is read — other Jira link types (Relates, Duplicates, Clones, and any custom link types) are ignored.
What does not map
Section titled “What does not map”This is the minimal computable slice. The following are deliberately out of scope for this importer — they are not imported, and no error is raised for their presence:
- Sprints and sprint assignment
- Assignees as resources (no resource records or allocations are created)
- Parent / subtask hierarchy — the WBS is flat; subtasks import as their own top-level tasks
- Epics and epic links
- Custom fields
- Saved filters / board views
- Start-date, due-date, and other fixed-date constraints — CPM derives dates from durations and dependencies
- Non-
Blockslink types (Relates, Duplicates, Clones, custom links) - Jira Cloud exports — Cloud has no XML export (Server / DC only)
- Any writeback to Jira — this is a one-way, read-only import
CPM needs only durations and dependencies to compute a critical path, so the excluded fields are not required to get a working schedule. Richer, multi-format import (including broader Jira coverage and a mapping-preview step) is on the roadmap.
Invalid and skipped input
Section titled “Invalid and skipped input”The import is validated before anything is written, so a messy export can never persist an infeasible schedule that would later crash the CPM / what-if engine.
- A cyclic or self-blocking set of
Blockslinks fails the import. If the derived dependency graph contains a cycle (A blocks B blocks … blocks A), the whole import is rejected and marked failed — no tasks or dependencies are created. CPM cannot schedule a cyclic network, so the importer refuses it up front rather than persisting a graph the engine can’t compute. - Self-referential links are silently skipped. A
Blockslink from an issue to itself is dropped (quarantined) with a warning; it does not fail the import. - Links to issues not in the export are silently skipped. A
Blockslink pointing at an issue that isn’t part of this XML (e.g. it was filtered out) is dropped with a warning — an issue outside the export can’t be scheduled. - Issues with no key, and duplicate keys, are skipped with a warning.
Skipped items are recorded as warnings on the import summary; only a genuine cycle (or an unparseable file) fails the import outright.
Using the API
Section titled “Using the API”The import authenticates with a bearer token ($JWT); $PROJECT_ID is the
destination project UUID. The endpoint accepts a single .xml file as multipart
form-data in the file field, and requires Project Manager or above.
# POST a Jira Server/DC XML export as multipart form-data (field: "file").# Requires project Admin. Default upload cap 25 MB (JIRA_IMPORT_MAX_UPLOAD_MB).curl -X POST \ -H "Authorization: Bearer $JWT" \ -F "file=@jira-export.xml" \ https://trueppm.example.com/api/v1/projects/$PROJECT_ID/import/jira/# 202 Accepted: {"detail": "Import queued.", "import_request_id": "<uuid>"}A 202 means the file was accepted and queued — not that the import has
finished. The import runs asynchronously and is durable: it is committed to
an outbox row before dispatch, so a brief task-broker outage does not lose it —
the request stays queued and is picked up automatically. A deterministic failure
(an unparseable file, or a cyclic graph) marks the request terminal so it is not
retried forever.
Only .xml is accepted. A different extension is rejected with 400 before any
parsing happens; a file above the size cap is rejected with 400 naming the
configured limit; a caller below Project Manager gets 403.
Configuration
Section titled “Configuration”The only operator-facing knob is the upload size cap, JIRA_IMPORT_MAX_UPLOAD_MB
(default 25 MB), documented in the
configuration reference.
Like the MS Project importer, Jira XML is parsed through defusedxml, which
refuses entity declarations and external-entity resolution — a “billion laughs”
or XXE payload is rejected at parse time. The parser treats every uploaded byte
as untrusted input; this protection is unconditional.