Sprint → milestone rollup

Linking a sprint to a Schedule-view milestone via Sprint.target_milestone makes that milestone’s percent_complete live. The number a PM sees on the Schedule view and the number a Scrum Master sees on the Sprints view are the same number, computed from the same sprint state, with no manual reconciliation step.

This closes the longest-standing gap between TruePPM’s agile and waterfall views: before this change, the link was display-only — the AdvancingToMilestone card showed the milestone’s name and date, but its progress drifted from the sprint’s real state until someone updated the Schedule view by hand.

When at least one sprint targets a milestone task:

  • The milestone’s percent complete rolls up live from sprint committed_* / completed_* snapshots and current task state. The Schedule-view task list shows the rolled-up value with a 🔒 lock indicator and the AdvancingToMilestone card shows the same number.
  • A sprint plan variance (positive = slip past the milestone, negative = ahead) appears next to the rolled-up value: Sprint plan: +3d slip or Sprint plan: -2d ahead. This is computed from the latest ACTIVE / PLANNED sprint’s finish_date against the milestone’s CPM date. Sprint dates are never automatically mutated.
  • A scope-changed chip appears when an active sprint’s current backlog points sum diverges from its activation-time committed_points snapshot. (Added in 0.3.) The percent stays bounded; the chip surfaces the discrepancy so the value remains honest. The chip is persistent and clickable — not a hover-only tooltip — and shows the net scope delta (+N / −M points). It appears in all three milestone surfaces: the Schedule-view task list, the milestone Overview drawer, and the sprint-workspace AdvancingToMilestone card. See scope-change audit chip below.
  • The milestone’s percent_complete becomes read-only against manual writes. The API rejects writes with a structured 400 (code: milestone_rollup_locked). To override, unlink or close the sprint first; the lock releases immediately.

Binding is what turns on every rollup above — until a sprint targets a milestone, none of it applies.

In the app. From the sprint panel, a Scheduler (or above) uses Link milestone — the action appears only while the sprint is unbound. It opens a dialog with a live reforecast preview (projected dates and a team-pace band, computed on the fly and persisted to nothing), then either mints a new milestone from the sprint goal or binds an existing milestone in the same project.

Over the API. POST /api/v1/sprints/{id}/promote-to-milestone/ (Scheduler+):

  • Body {} — mints a new Task(is_milestone=true) from the sprint goal, dated at the sprint finish, and binds it. Returns 201. Optional {"name", "target_date"} rename or re-date the minted milestone (create-mode only; both are ignored when milestone_id is given).
  • Body {"milestone_id": "<uuid>"} — binds an existing milestone in the same project. Returns 200. Re-binding the milestone already bound is an idempotent 200.

A dry run for the dialog is available at GET /api/v1/sprints/{id}/reforecast-preview/?milestone_id=<uuid> (any project member; omit milestone_id to preview the to-be-minted milestone).

To bind a different milestone, unbind first — the binding never silently re-points. POST /api/v1/sprints/{id}/unbind-milestone/ (Scheduler+) clears the binding and its provenance and recomputes the freed milestone’s rollup. It is no-op-safe: an already-unbound sprint returns 200 unchanged.

StatusCode / bodyWhen
409{"code": "sprint_already_bound", "current_milestone_id": "<uuid>"}Binding a different milestone while the sprint is already bound. Unbind first.
400{"milestone_id": "Milestone not found in this project."}milestone_id does not name a milestone in the sprint’s project.

The rollup uses points by default and falls back to task counts when no team member sized in points:

if any sprint has committed_points > 0:
percent_complete = min(100, completed_points / committed_points * 100)
basis = "points"
elif any sprint has committed_task_count > 0:
percent_complete = min(100, completed_task_count / committed_task_count * 100)
basis = "tasks"
else:
percent_complete = null # falls back to manual value
basis = "none"

Sums are across all sprints targeting the milestone (completed + active

  • planned), reflecting cumulative progress toward the milestone. A milestone targeted by three sprints reports cumulative completion, not the most recent sprint alone.

CANCELLED sprints are skipped entirely — they contribute nothing to either the denominator or the numerator.

The scope-changed chip is the milestone-side entry point into the same audit the team sees on the Board. One click opens a read-only scope-change audit drawer listing each per-task scope change behind the net delta — who added or removed the task, when, the task, its point value, and whether the change is accepted, pending, or rejected.

The chip is rendered identically in all three milestone surfaces — the Schedule-view task list, the milestone Overview drawer, and the sprint-workspace AdvancingToMilestone card — so the PM (looking from the Gantt/Overview) and the team (looking from the sprint workspace) open the same audit from either side. There is no team-private vs PM-private split here: a scope change is a fact about the sprint’s commitment, not a velocity signal, so both audiences read it.

The drawer is backed by GET /sprints/{id}/scope-changes/ — the same endpoint that powers the Board mid-sprint scope-change badge. It is a visibility surface only; it never accepts or rejects a change.

Screenshot TODO: a milestone row in the Schedule-view task list showing the persistent Scope changed +5 / −2 pts chip, and the open scope-change audit drawer.

Real-time updates use a new milestone_rollup_updated WebSocket event. The payload is aggregated only — never includes per-assignee task lists or raw committed/completed point counts:

{
"milestone_id": "<uuid>",
"percent_complete": 73.5,
"rollup_basis": "points",
"variance_days": 3,
"sprint_scope_changed": false,
"sprint_count": 1
}

This deliberate constraint preserves team autonomy: PMO-visible surfaces see rolled-up milestone health, but per-team velocity and individual assignments stay on the sprint side and remain bounded by the sprint board’s permissions.

  • On sprint state change: activate, cancel, close — recompute fires in the same transaction that runs the existing snapshot.
  • On sprint create / update / delete: re-link to a new milestone recomputes both the old and new milestones so neither holds a stale value.
  • On task save: tasks in a sprint with a target milestone recompute the rollup live (best-effort — broker failures don’t block the underlying task write; the next state change reconciles).

The authoritative recompute always runs inside the SprintCloseRequest outbox drain on close, after the immutable completed_* snapshot lands, so the final value is correct even if a live recompute was missed during an outage.

Sprints are usually closed by the team, often outside the project manager’s working session. So when closing a sprint reforecasts a bound milestone and that reforecast materially moves its likely finish or confidence, TruePPM notifies the project’s manager cohort (Project Manager and Project Admin roles) with a short schedule-language summary — for example, “Sprint 4 closed — GA Launch likely finish Jul 20 → Aug 1 (est. by Aug 15, medium confidence).” It arrives in-app and by email, and clicking it opens the milestone in the Schedule.

The summary carries dates and a confidence label only — never velocity points, matching the signal-privacy model. A recompute that changes nothing produces no notification, so a no-op close is never noise. Any recipient can mute either channel from Settings → Notifications.

There is no override flag in v1. To edit a milestone’s percent manually:

  1. Unlink the sprint by setting target_milestone = null on the sprint, or
  2. Close all targeting sprints.

The milestone field unlocks immediately when the last live targeting sprint is gone.

  • Rollup is single-project scope. A milestone in Program A and a sprint in Program B cannot be linked. Cross-program milestone aggregation is an Enterprise concern.
  • Variance is display only — there is no “shift the milestone” button. The PM owns the Schedule view; the rollup advises but never mutates dates.
  • Portfolio-level milestone health rollup (across many projects, for a PMO dashboard) is part of trueppm-enterprise.