CSV / Excel import

Most teams that have never used dedicated project software still run a real schedule — in Excel, or in a Google Sheet shared over email. For them the barrier to adopting TruePPM is not features, it is getting the existing plan in without retyping it. CSV / Excel import removes that barrier: upload the sheet, confirm what each column means, and TruePPM builds a CPM-schedulable network from it — tasks, durations, dates, a WBS hierarchy, dependencies, and assignees.

This is also the import path for the many tools that export CSV. Asana, Trello, Basecamp and others all produce a CSV you can feed directly to this endpoint.

The importer expects a header row followed by task rows. Nothing else is required — every column below is optional except the task name.

Download the known-good template if you want a target shape to paste into.

TruePPM fieldHeader spellings recognized
Task name (required)Name, Task, Title, Task Name, Activity, Summary
IDID, Task ID, UID, No, Number, Ref, Key
WBS / phaseWBS, WBS Code, Phase, Level, Outline, Outline Number
DurationDuration, Days, Effort, Estimate, Work Days
StartStart, Begin, Start Date, Planned Start
FinishFinish, End, Due, Due Date, Planned Finish
% complete% Complete, Percent Complete, Done, Progress
AssigneeAssignee, Owner, Resource, Assigned To, Responsible
PredecessorsPredecessors, Depends On, Dependency, Blocked By, After
MilestoneMilestone
NotesNotes, Description, Comment, Detail
LabelsLabels, Label, Tags, Tag, Category, Component, Stream, Workstream

Matching is case-insensitive, punctuation-insensitive, and plural-aware, so % Complete, %complete and Percent Completes all resolve to the same field. Anything the importer cannot place is shown to you as unmapped rather than silently dropped, and you can assign it yourself before committing.

Most fields take exactly one column — two Name columns is a mistake, so the second is reported as a duplicate and dropped rather than merged.

Labels and Predecessors are the exceptions. Both accept several source columns, and the values are unioned onto the task:

  • A sheet carrying Tags, Component and Team gets all three as labels.
  • An MS Project export that spreads dependencies across Predecessor 1 and Predecessor 2 gets both links. The same reference appearing in two columns is one relationship, not two.

If auto-detection places only one of them, map the others to the same field yourself in the column overrides.

One cell can carry several labels, separated by , ; or / — the same convention the assignee column uses. safety, rework becomes two labels.

Names are matched against your project’s existing label catalog, case-insensitively, so importing a sheet that says Safety into a project that already has safety reuses the existing label instead of creating a near-duplicate you then have to merge. The catalog’s spelling wins. Labels that do not exist yet are created and given distinct colors.

Labels are project-scoped: a label of the same name in another project is a different label and is not matched.

An import is capped at 100 distinct labels and 20 per task, and label names are shortened to 50 characters. Exceeding a cap does not fail the import — the excess is reported as a row warning and everything else is imported.

  • Blank rows — ignored entirely.
  • Rows whose first cell starts with # — treated as comments, so you can annotate the sheet without breaking the import.

TruePPM builds a real WBS tree, and it recognizes the two ways spreadsheets actually encode one:

A WBS / outline column. Dotted codes map straight to the tree:

WBS Name
1 Discovery
1.1 Stakeholder interviews
1.2 Requirements draft
2 Build
2.1 Data model

Indentation in the name column. Two spaces (or one tab, or one leading dot) per level — the convention most hand-built sheets use:

Name
Phase One
Design
Build
Backend
Frontend

Both produce the same nested schedule.

The predecessor column accepts the MS Project shorthand, comma- or semicolon-separated:

CellMeaning
3Finish-to-Start on task 3
3FS+2dFinish-to-Start on task 3, with 2 days of lag
5SSStart-to-Start with task 5
9FS-1dFinish-to-Start with 1 day of lead
6,7Two Finish-to-Start predecessors

References resolve against your ID column when the sheet has one, and against row position otherwise — so both an MS Project-style export and a hand-typed sheet work without changes.

Durations may be written as 5, 5d, 5 days, 16 hours (converted on an 8-hour day) or 2 weeks. A duration of 0 marks the row as a milestone.

Percent complete accepts 50, 50%, or Excel’s native 0.5.

Dates are read as YYYY-MM-DD unambiguously. For slash dates the importer scans the whole file before deciding: if any row is unambiguously day-first (13/04/2026 cannot be a month), every slash date is read day-first. With no evidence either way it assumes month/day/year and tells you which convention it used in the import warnings — a silently-guessed date order is a data-integrity bug, not a formatting detail.

Open a project’s Schedule, then Project actions → Import from spreadsheet (CSV/Excel)…. The wizard walks the three steps below so you never have to call the API yourself.

Step 1 — Upload. Drag a .csv, .tsv, .txt, .xlsx, or .xlsm file onto the drop zone, or pick one. Files over the size cap are rejected before the upload runs, so you do not wait on a request that is certain to fail.

Step 2 — Map columns. Every detected column is listed with the TruePPM field it will import into, already filled in from auto-detection — you confirm rather than map from scratch. Change any dropdown that is wrong, or set one to Don’t import to ignore that column. The first parsed rows sit underneath, so you can see what the mapping actually produces.

If a required field has no column mapped to it, Next is disabled and the wizard says which field is missing. This is deliberate: a spreadsheet with no recognizable task-name column imports zero tasks, and a silent no-op is a worse outcome than a blocked button.

Changing a mapping and pressing Re-check mapping re-runs the preview on the server, so what you confirm on step 3 is what the parser genuinely produced — not a client-side guess at what your change would do.

Step 3 — Confirm and import. The wizard shows the row count, how many tasks and resources will be created, and names every column that will not be imported rather than dropping them quietly. Rows that will be lost and rows that will merely land with a field defaulted are counted separately, because they are different decisions.

When it finishes, you get the number of tasks created and, if any rows had problems, a list of them by spreadsheet line number so you can fix them at source. View schedule takes you to the imported plan.

The wizard is a client of the same three endpoints, documented here for anyone scripting an import.

POST /api/v1/projects/{id}/import/csv/preview/ parses the file and returns the detected column mapping, the first ten parsed rows, the task and resource counts, and any row-level problems. It writes nothing. Use it to confirm the mapping before committing.

Send a column_map alongside the file — a JSON object of {"header": "field"} — to pin a column explicitly. An override always beats auto-detection. Map a column to "" to have it ignored.

POST /api/v1/projects/{id}/import/csv/ queues the import and returns 202 with an import_request_id. The import runs asynchronously; poll GET /api/v1/projects/{id}/import/csv/{import_request_id}/ for its terminal status and summary.

Partial success is a result, not a failure

Section titled “Partial success is a result, not a failure”

A real spreadsheet has a few bad cells in it. The importer treats that as normal: a row with an unreadable date, an unreadable duration, or a predecessor that matches nothing still imports, minus that one field, and the problem is reported against its row number — the same number you see in Excel’s row gutter.

{
"tasks_created": 5,
"row_error_count": 2,
"error_count": 0,
"warning_count": 2,
"row_errors": [
{ "row": 3, "column": "Start", "code": "bad_date", "severity": "warning",
"message": "Could not read 'not-a-date' as a date; the start was left unset." },
{ "row": 5, "column": "Predecessors", "code": "unknown_predecessor", "severity": "warning",
"message": "Predecessor '99' does not match any row; the link was skipped." }
]
}

Every diagnostic carries a severity, and it answers exactly one question:

SeverityMeaning
warningThe row imported, with one field dropped or defaulted — a bad date, an unreadable duration, a predecessor that matched nothing.
errorThe row did not import at all. Today the only cause is a row with no task name.

They are counted separately (error_count / warning_count) rather than totalled, because the two are not the same event: seven warnings means seven tasks landed slightly lossy, while one error means a row of your spreadsheet is simply not there. Both are returned by the preview endpoint too, so you can see the split before committing.

Only a structurally unusable file fails outright: no header row, no column that could be the task name, unreadable bytes, or a cyclic predecessor column.

Import requires the Scheduler role or above (Scheduler, Admin, or Owner) on the destination project. Members and Viewers are denied. The preview endpoint is gated identically — it parses an uploaded file, so it is not a lighter-privilege surface just because it saves nothing.

LimitDefaultSetting
Upload size10 MBCSV_IMPORT_MAX_UPLOAD_MB
Data rows5 000CSV_IMPORT_MAX_ROWS
.xlsx uncompressed size100 MBCSV_IMPORT_MAX_UNCOMPRESSED_MB

Rows past the cap are reported back to you as skipped, not silently dropped. See CSV / Excel import limits for operator configuration.

  • Only the first worksheet is imported. Extra sheets are ignored and you are told how many were skipped.
  • Values, not formulas. The workbook is read with cached values, so a cell containing =SUM(...) imports as the number Excel last computed.
  • .xlsx and .xlsm are accepted. The legacy .xls format is not — re-save it as .xlsx or export it as CSV.

GET /api/v1/import-templates/csv/ returns a known-good CSV with the canonical headers and a worked example demonstrating nesting, a lagged dependency, a Start-to-Start link, a zero-duration milestone, and a multi-value Labels cell.

Deliberate exclusions — a spreadsheet does not carry them, and inventing them would be worse than leaving them out:

  • Calendars and working-time exceptions. Imported tasks use the project’s calendar.
  • Baselines, sprints, and board columns. Set these up in TruePPM after import.
  • Three-point (PERT) estimates. A single duration column maps to duration only.
  • Cross-project dependencies. Import is scoped to one project.
  • Resource rates, capacity, and calendars. Assignees are matched or created by name; everything else about them stays unset.